DOC - Permit Finaled | 11/10/2014 | 11/10/2014 | 11/10/2014 | P | PASS |
Andy J. Long
|
|
|
|
Site Final | 11/10/2014 | 11/10/2014 | 11/10/2014 | P | PASS |
Andy J. Long
|
|
|
Construction complete. Parking lot paved and landscaping installed. No loose sediment or construction materials at site. All permits finaled. ESC conditions satisfied.
|
Random Inspection | 10/6/2014 | 10/6/2014 | 10/6/2014 | A | PASS |
Andy J. Long
|
|
|
Office building is near completion. Landscaping is in progress. No trackout or non-stormwater discharges at site. Permit is posted. Will be finished soon. No corrections.
|
General Inspection | 9/15/2014 | 9/15/2014 | 9/15/2014 | | PASS |
Andy J. Long
|
|
|
WIP. No trackout, spills, or other issues observed. The frame is up for warehouse, stormwater structures have BMP protection.
|
General Inspection | 7/29/2014 | 7/29/2014 | 7/29/2014 | | PASS |
Andy J. Long
|
|
|
Frame of building is erected and parking lot is halfway complete. WIP on interior. No trackout, discharges, dust, or other ESC issues at site.
|
General Inspection | 6/13/2014 | 6/13/2014 | 6/13/2014 | | PASS |
Evan Jenkins
|
|
|
no issues
|
Site Preparation | 4/28/2014 | 4/28/2014 | 4/28/2014 | P | PASS |
Andy J. Long
|
|
|
Dave Oneal ####-####
Wattles installed. Work has began per phone conversation with Dave on Friday 4/25. Will need to make sure there is minimal trackout to Albatross. No MS4 structures in area. Approved.
|
Issue & PRINT permit COM | | | 4/22/2014 | | DONE |
|
|
|
|
General Inspection | 4/21/2014 | 4/21/2014 | 4/21/2014 | | PASS |
Andy J. Long
|
|
|
No activity. Building permit is now ready for pick up. Left VM with Dave O'neil to inform him grading and grubbing may commence. No MS4 on Albatross.
|
General Inspection | 3/4/2014 | 3/5/2014 | 3/5/2014 | A | PASS |
Andy J. Long
|
|
|
rescheduled from 3/4
No activity or disturbance.
|
General Inspection | 3/4/2014 | 3/4/2014 | 3/4/2014 | | CANC |
Andy J. Long
|
|
|
rescheduled for 3/5. Unable to reach due to makeup inspections from last week's absence.
|
General Inspection | 1/14/2014 | 1/14/2014 | 1/14/2014 | | PASS |
Andy J. Long
|
|
|
No construction activity has started. Permit was paid for online before issued, so is not actually issued - software error. BLD permit still under review. ESC plan submitted and approved. 2nd week of January.
|
Routing - Erosion and Sediment | 1/10/2014 | | 1/10/2014 | | DONE |
Andy J. Long
|
|
|
ESC plan submitted and approved. Need to designate valid RP before permit is issued.
|
Permit Ready to Issue | | | 7/17/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/17/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 17 2013 12:04PM
|