General Inspection | 5/8/2014 | 5/8/2014 | 5/8/2014 | | PASS |
Andy J. Long
|
|
|
Finaled.
|
DOC - Permit Finaled | 5/8/2014 | 5/8/2014 | 5/8/2014 | P | PASS |
Andy J. Long
|
|
|
House complete and occupied. Adajacent townhome still under construction but Elevation Ridge looks to be in compliance. No further inspections for this permit. ESC conditions satisified.
|
General Inspection | 4/7/2014 | 4/7/2014 | 4/7/2014 | | PASS |
Andy J. Long
|
|
|
Near completion with some landscaping in progress and interior work. No violations observed.
|
General Inspection | 3/7/2014 | 3/7/2014 | 3/7/2014 | | FAIL |
Andy J. Long
|
|
|
There appears to be a spill of green antifreeze into the gutter behind the Boise Basin Electric work van. Followed spill about 50-75 feet in north gutter.
Called Clint RP. He is on his way to apply spill absorbent and discuss with contractor.
Waited for RP to arrive. We believe spill is from cement pumping truck which may have leaked hydrauic oil. Clint started sweeping while I was there, applying spill absorbent, and called Brundage Bone to come assist in clean up.
Positive response. Will check back for clean up conditions.
|
General Inspection | 2/4/2014 | 2/4/2014 | 2/4/2014 | | PASS |
Andy J. Long
|
|
|
Elevation Ridge townhome construction in compliance.
|
General Inspection | 1/1/2014 | 1/1/2014 | 1/2/2014 | | CANC |
Evan Jenkins
|
|
|
holiday
|
General Inspection | 11/27/2013 | 11/27/2013 | 11/27/2013 | | PASS |
Andy J. Long
|
|
|
No activity. BMPs installed, permit posted.
|
General Inspection | 10/23/2013 | 10/23/2013 | 10/23/2013 | | PASS |
Andy J. Long
|
|
|
Permit posted with permit details. Silt fence protecting hillside is trenched. Foundation is laid, vertical construction remaining.
|
Site Preparation | 9/17/2013 | 9/17/2013 | 9/18/2013 | P | PASS |
Eric Strole
|
|
|
Clint Phone #: ###-####
|
Site Preparation | 9/17/2013 | 9/17/2013 | 9/17/2013 | P | CANC |
Bob Archibald
|
|
|
kristy Phone #: ###-#### Inspection cancelled from web by: Barbara Stitt
|
Issue & PRINT permit SFD | | | 8/15/2013 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 8/8/2013 | | 8/9/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Application received | | | 7/31/2013 | | |
|
|
|
|