Site Final | 9/25/2014 | 9/26/2014 | 9/26/2014 | A | PASS |
Andy J. Long
|
|
|
Nick Phone #: ###-####
RP onsite removing DI bag in MS4 on Cassia, final gutter sweep, and permit sign. Project has been compliant through duration. Parking lot, curbing, and landscaping complete.
ESC conditions satisfied.
|
DOC - Permit Finaled | 9/26/2014 | 9/26/2014 | 9/26/2014 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/18/2014 | 9/18/2014 | 9/18/2014 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 | | PART |
Andy J. Long
|
|
|
Old parking lot asphalt has been removed. New lot has been graded but is awaiting pavement and landscaping. Some minor trackout to Cassia and sediment in gutter directly in front of work area is present. Need to sweep up after parking lot is paved.
|
Site Preparation | 7/16/2014 | 7/17/2014 | 7/17/2014 | A | CANC |
Evan Jenkins
|
|
|
George (or Jim Perkins ###-####) Phone #: ###-#### Andy already inspected the site on the 15th (2 days ago). I called the RP and he said he wasn't sure if there had been an inspection yet, so he called in for a Site Prep Inspection. No reason to inspect this simple project within 2 days of each other
|
General Inspection | 7/15/2014 | 7/15/2014 | 7/15/2014 | | PASS |
Andy J. Long
|
|
|
WIP. Scraping existing parking lot asphault and hauling away. No trackout or discharges observed.
|
Issue & PRINT permit COM | | | 7/8/2014 | | DONE |
|
|
|
|
Application received | | | 9/9/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 9 2013 4:48PM
|