DOC - Permit Finaled | 5/1/2015 | 5/1/2015 | 5/1/2015 | P | PASS |
Andy J. Long
|
|
|
Landscaped, stabilized, and site cleaned. Only 2 more parcels along Old Hickory and then will request DI bags to be removed.
ESC conditions satisfied.
|
Aging Inspection | 4/2/2015 | 4/2/2015 | 4/2/2015 | | PASS |
Andy J. Long
|
|
|
|
Site Preparation | 10/28/2014 | 10/28/2014 | 10/28/2014 | P | PASS |
Andy J. Long
|
|
|
Clint Phone #: ###-####
Permit posted. Subdivision BMPs installed and have adequate capacity (lined cement washout; DI sediment sacks). Tahoe projects adjacent to this site are ongoing and in compliance.
|
Issue & PRINT permit SFD | | | 10/22/2014 | | DONE |
|
|
|
|
Application received | | | 10/8/2013 | | |
|
|
|
|