General Inspection | 9/18/2014 | 9/19/2014 | 9/19/2014 | P | PASS |
Evan Jenkins
|
|
|
see final
|
DOC - Permit Finaled | 9/19/2014 | 9/19/2014 | 9/19/2014 | P | PASS |
Evan Jenkins
|
|
|
project complete no esc issues
|
General Inspection | 9/18/2014 | 9/18/2014 | 9/18/2014 | | CANC |
Andy J. Long
|
|
|
rescheduled.
|
General Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 7/18/2014 | 7/18/2014 | 7/18/2014 | | PASS |
Evan Jenkins
|
|
|
Project appears complete only ESC issues is that the stormwater pond needs to be stabilized
|
General Inspection | 6/17/2014 | 6/17/2014 | 6/17/2014 | | PASS |
Evan Jenkins
|
|
|
work in pregress new entry paved no esc issues at time of inspection
|
General Inspection | 5/14/2014 | 5/14/2014 | 5/14/2014 | | PASS |
Evan Jenkins
|
|
|
Construction on building looks near complete no constructing new access road
|
General Inspection | 4/9/2014 | 4/9/2014 | 4/9/2014 | | PASS |
Evan Jenkins
|
|
|
no esc issues at time of inspection
|
General Inspection | 3/6/2014 | 3/6/2014 | 3/6/2014 | | PASS |
Evan Jenkins
|
|
|
Concrete Slab/foundation poured Concrete washout look good Construction SIgnage Posted
|
General Inspection | 1/30/2014 | 1/30/2014 | 1/30/2014 | | PART |
Evan Jenkins
|
|
|
No ESC Issues at time of inspection SWPPP not onsite. Attempted to call Big Bite Contruction Owner and left VM describing that the RP's contact cell number needs to be written on the Yellow Construction SIgn and SWPPP needs to remain onsite throughout the life of the project
|
Issue & PRINT permit COM | | | 1/22/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - Erosion and Sediment | 12/13/2013 | | 12/13/2013 | | PASS |
Andy J. Long
|
|
|
ESC plan/SWPPP submitted and approved.
|
Application received | | | 12/6/2013 | | |
|
|
|
|