General Inspection | 5/14/2014 | 5/14/2014 | 5/14/2014 | | PASS |
Andy J. Long
|
|
|
Finaled.
|
DOC - Permit Finaled | 5/14/2014 | 5/14/2014 | 5/14/2014 | P | PASS |
Andy J. Long
|
|
|
Project is complete. All disturbed areas stabilized and construction supplies removed. ESC permit conditions.
|
Site Preparation | 3/10/2014 | 3/10/2014 | 3/10/2014 | A | PASS |
Andy J. Long
|
|
|
11:30 AM. site prep
Met RP and contractor onsite. Will be install exterior double chamber grease trap. Permit is posted in window of hotel, downstream DI has inlet protect. Wattles onsite to contain any stockpiles that may occur. Excavation to start on Wednesday. Approved.
|
Issue & PRINT permit COM | | | 3/7/2014 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Erosion and Sediment | 2/10/2014 | | 2/10/2014 | | DONE |
Andy J. Long
|
|
|
ESC plan waiver submitted. Need to designated valid RP to get permit.
|
Application received | | | 1/6/2014 | | |
|
|
|
|