DOC - Permit Finaled | 3/13/2015 | 3/13/2015 | 3/13/2015 | P | PASS |
Andy J. Long
|
|
|
|
Site Final | 3/13/2015 | 3/13/2015 | 3/13/2015 | P | PASS |
Andy J. Long
|
|
|
Home is complete, surrounding areas have been cleaned and hard surfaces swept. Yard is landscaped and stabilized with sod.
ESC permit conditions satified.
|
General Inspection | 2/27/2015 | 2/27/2015 | 2/27/2015 | | PASS |
Andy J. Long
|
|
|
Home is complete and yard has been landscaped with sod. HIllside bank areas have their natural vegetation. No violations at site.
Will do final check once other trades are finaled.
|
DOC - Permit Finaled | 2/27/2015 | 2/27/2015 | 2/27/2015 | P | PASS |
Andy J. Long
|
|
|
(This activity was added in error so we have changed the case status back to Issued.)
|
General Inspection | 2/12/2015 | 2/12/2015 | 2/12/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 1/28/2015 | 1/28/2015 | 1/28/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 1/13/2015 | 1/13/2015 | 1/13/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 12/29/2014 | 12/29/2014 | 12/29/2014 | | PASS |
Andy J. Long
|
|
|
No activity currently. House is built with interior work remaining as well as landscaping. No ESC violations.
|
General Inspection | 12/12/2014 | 12/12/2014 | 12/12/2014 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 11/27/2014 | 11/27/2014 | 11/28/2014 | | CANC |
Evan Jenkins
|
|
|
holiday
|
General Inspection | 11/12/2014 | 11/12/2014 | 11/12/2014 | | PASS |
Andy J. Long
|
|
|
No activity or changes at site since last inspection. Interior work remaining, landscaping/yard not yet installed. Culdesac is clean and sediment contained by existing vegetative buffer.
|
General Inspection | 10/28/2014 | 10/28/2014 | 10/28/2014 | | PASS |
Andy J. Long
|
|
|
No activity at time of inspection. Culdsac is free of sediment; vegetative barrier around yard has been undisturbed. House near completion, not yet landscaped. No corrections required.
|
General Inspection | 10/13/2014 | 10/13/2014 | 10/13/2014 | | PASS |
Andy J. Long
|
|
|
Yard is not yet landscaped, but unvegetated area around home is surrounded by vegetative buffer. Trash is contained, no trackout or other ESC violations observed. Exterior is mostly complete, WIP on interior.
|
General Inspection | 9/26/2014 | 9/26/2014 | 9/26/2014 | | PASS |
Andy J. Long
|
|
|
Vegetated buffer surrounds home. No trackout, culdesac is clean. Permit posted on back of large Bruno Built sign (currently blown over)
No corrections at this time.
|
General Inspection | 9/11/2014 | 9/11/2014 | 9/11/2014 | | PASS |
Andy J. Long
|
|
|
No correcctions at site. Culdesace is clean, permiter vegetative barrier has been maintained through duration of project. Trash and materials are contained. Approved.
|
General Inspection | 8/27/2014 | 8/27/2014 | 8/27/2014 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 8/8/2014 | 8/8/2014 | 8/8/2014 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 7/24/2014 | 7/24/2014 | 7/24/2014 | | PASS |
Andy J. Long
|
|
|
WIP. No violations observed. Mesa Verde culdesac has very little trackout.
|
General Inspection | 7/9/2014 | 7/9/2014 | 7/9/2014 | | PASS |
Andy J. Long
|
|
|
Vegetative perimeter has remained intact. Culdesac and sidewalks are clean. Permit posted on back of construction sign. Approved.
|
General Inspection | 6/24/2014 | 6/24/2014 | 6/24/2014 | | PASS |
Andy J. Long
|
|
|
Frame is up. Stucco crew is up. Told them to contain their washout, though there were no violations at the time. The vegetated barrier was preserved and culdesac clean. Approved.
|
General Inspection | 6/6/2014 | 6/6/2014 | 6/6/2014 | | PASS |
Andy J. Long
|
|
|
No violations. Surrounded by vegetative buffer that has been carefully maintained. Culdesac is clean.
|
General Inspection | 5/22/2014 | 5/22/2014 | 5/22/2014 | | PASS |
Andy J. Long
|
|
|
Permit posted on back of contractor sign. Vegetative perimter has been maintained. Minimal trackout, contractors parking on street. No violations.
|
General Inspection | 5/7/2014 | 5/7/2014 | 5/7/2014 | | PART |
Andy J. Long
|
|
|
Need DI bag or sediment mat at DI on Windsong just below Mesa Verde on the left. Permit posted, minimal trackout to be swept at end of day.
|
General Inspection | 4/18/2014 | 4/18/2014 | 4/18/2014 | | PASS |
Andy J. Long
|
|
|
John Brown excavation onsite. Washout pit is being used. Vegetative buffer discussed in site prep is containing sediment onsite, but will need to continue to watch that stockpile on the Windsong side. No corrections at this time.
|
Site Preparation | 4/1/2014 | 4/2/2014 | 4/2/2014 | A | PASS |
Andy J. Long
|
|
|
Robert Phone #: ###-####
Conference with contractor Robert Bruno and excavator Jon Brown.
Downhll wattles on ESC plan are not necessary for initial phases due to existing vegetative buffer and berm. Wattles will be used if any stockpiling in area will occur for an extended period.
Permit posted, portapot is staked down, construction entrance will be installed once foundation is in.
Approved.
|
Issue & PRINT permit SFD | | | 3/25/2014 | | |
|
|
|
|
Application received | | | 2/3/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 3 2014 3:19PM
|