General Inspection | 10/7/2014 | 10/7/2014 | 10/7/2014 | | PASS |
Evan Jenkins
|
|
|
see final
|
DOC - Permit Finaled | 10/7/2014 | 10/7/2014 | 10/7/2014 | P | PASS |
Evan Jenkins
|
|
|
Pool Complete/ vegetation re-established no esc issues
|
General Inspection | 9/5/2014 | 9/5/2014 | 9/5/2014 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 8/5/2014 | 8/5/2014 | 8/5/2014 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 7/4/2014 | 7/4/2014 | 7/7/2014 | | CANC |
Andy J. Long
|
|
|
holiday
|
General Inspection | 6/3/2014 | 6/3/2014 | 6/3/2014 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/1/2014 | 5/1/2014 | 5/1/2014 | | PASS |
Evan Jenkins
|
|
|
Pool appears complete No ESC Issues All permits still open. Next inspection ESC Permit will most likely be finaled
|
General Inspection | 3/26/2014 | 3/26/2014 | 3/26/2014 | | PASS |
Andy J. Long
|
|
|
Pool is under construction. Staging area is in backyard surrounded by vegetated buffer. Approved.
|
Issue & PRINT permit SFD | | | 3/19/2014 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 2/27/2014 | | 3/4/2014 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. Valid RP provided (Troy # ###-####)
|
Application received | | | 2/27/2014 | | |
|
|
|
|