General Inspection | 8/29/2014 | 8/29/2014 | 8/29/2014 | | PASS |
Andy J. Long
|
|
|
Finaled.
|
DOC - Permit Finaled | 8/29/2014 | 8/29/2014 | 8/29/2014 | P | PASS |
Andy J. Long
|
|
|
Retaining wall for new SFH at 957 Capitola has been constructed. The home is now under construction and covered under a seperate permit ESC14-00157. Conditions satisified for this scope of work.
|
General Inspection | 7/29/2014 | 7/29/2014 | 7/29/2014 | | PASS |
Andy J. Long
|
|
|
Permit posted. No work at time of inspection.
|
General Inspection | 6/25/2014 | 6/25/2014 | 6/25/2014 | | PASS |
Andy J. Long
|
|
|
No activity at time of inspection. Sidewalk and gutter are very clean, no sediment or trackout from site. The lot has been grubbed, but the wall is not yet installed.
|
Site Preparation | 5/21/2014 | 5/21/2014 | 5/21/2014 | P | PASS |
Andy J. Long
|
|
|
Met RP Clyde onsite to discuss project. Retaining wall soil that is excavated will be tested and used as backfill if possible.
There is 1 storm drain across the street that may required protection. No surface waters adjacent to site. Approved for construction. Home is under seperate ESC permit.
|
General Inspection | 5/1/2014 | 5/1/2014 | 5/1/2014 | | NR |
Andy J. Long
|
|
|
No activity, no BMPs installed yet. Need to schedule a site prep when ready.
|
Issue & PRINT permit SFD | | | 4/24/2014 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | | 4/4/2014 | | PASS |
Andy J. Long
|
|
|
Discussed project with contractor/RP. ESC map for home is sufficient. No further requirements for ESC, just need zoning and PW approval for associated BLD permit
|
Routing - Erosion and Sediment | 3/11/2014 | | 3/11/2014 | | FAIL |
Andy J. Long
|
|
|
ESC plan is not specific to this phase of the project. Include construction schedule and narrative in ESC plan. Review ESC plan checklist requirements
|
Application received | | | 3/7/2014 | | |
|
|
|
|