Site Final | 11/12/2015 | 11/12/2015 | 11/12/2015 | P | PASS |
Andy J. Long
|
|
|
BLD for home is finaled and it is now occupied. Yard landscaped and driveway is complete. Warm Springs Ave bikelane and sidewalk are free of loose sediment.
Pool house and pool structures covered under ESC15-00417.
|
Aging Inspection | 10/19/2015 | 10/19/2015 | 10/19/2015 | | CANC |
Andy J. Long
|
|
|
|
Aging Inspection | 8/18/2015 | 8/18/2015 | 8/18/2015 | | PASS |
Evan Jenkins
|
|
|
No Issues observed at this time. There has been no BLD inspection since 1-9-15
|
Aging Inspection | 6/16/2015 | 6/16/2015 | 6/16/2015 | | PASS |
Evan Jenkins
|
|
|
|
Aging Inspection | 4/15/2015 | 4/15/2015 | 4/15/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: no esc issues
|
Aging Inspection | 2/12/2015 | 2/12/2015 | 2/12/2015 | | PASS |
Andy J. Long
|
|
|
WIP. No trackout to Warm Springs.
Need to sweep driveway apron and bikelane is all. No other violations.
|
Random Inspection | 12/9/2014 | 12/9/2014 | 12/9/2014 | P | PART |
Andy J. Long
|
|
|
Trackout from site onto Warm Springs and into bike lane needs to be swept. On site, BMPs, fencing, or signage should be installed to keep vehicles off the muddy area and on the sandy driveway base.
Called RP/GC Clive to make correction.
|
BMP Violation | 9/4/2014 | 9/4/2014 | 9/4/2014 | P | PASS |
Andy J. Long
|
|
|
Uncontained trash has been collected and placed inside a newly constructed trash bin. Correction from 9/2 has been completed. No other violations. Lots of work in front of site on Warm Springs by ACHD/utility crew.
|
Complaint Inspection | 9/2/2014 | 9/2/2014 | 9/2/2014 | P | PART |
Andy J. Long
|
|
|
complaint from neighbor not containing trash in proper receptacles therefore is being spread onto other properties. Also dirt and dust spread to off of construction site.
Dirt trackout and dust appears to be mostly related to the road and utility work that is occuring in front of site on Warm Springs.
Did observe that not all trash is contained as it should be.
Correction request issued to RP/GC Clive Culpan:
1. Clean up uncontained trash and debris 2. Provide larger capacity trash container/enclosure.
|
Site Preparation | 7/23/2014 | 7/23/2014 | 7/23/2014 | P | PASS |
Andy J. Long
|
|
|
There is more that 50 feet of buffer as well vegetation between stockpile and Warm Springs creek Most of stockpile will be offhauled if not backfilled.
Permit posted. No trackout from dump trucks. Approved.
|
Permit Ready to Issue | | | 7/15/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue & PRINT permit SFD | | | 7/15/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 5/13/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 13 2014 4:12PM
|