General Inspection | 12/3/2014 | 12/3/2014 | 12/3/2014 | | PASS |
Andy J. Long
|
|
|
This portion of Cancer Survivor Pavillion project is complete per Boise P&R project manager Toby. All disturbed area is stabilized and no loose sediment or stockpiles of material. The second phase of project is ongoing and temporarily inactive. Activity covered under ESC14-00094 and a CGP eNOI.
|
DOC - Permit Finaled | 12/3/2014 | 12/3/2014 | 12/3/2014 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/17/2014 | 11/17/2014 | 11/17/2014 | P | PASS |
Andy J. Long
|
|
|
Sidewalk, parking lot and walls for cancer pavillion are complete. No equipment or disturbed areas remaining at site for scope of work for this permit. BLD permit still open. Area of disturbance next to pond is covered under ESC14-00094. Need to check to see if other parking lot to the south of pond and connected to Pavillion area is also complete.
|
General Inspection | 11/13/2014 | 11/13/2014 | 11/14/2014 | | CANC |
Evan Jenkins
|
|
|
due to dangerious snow conditions/road ways, unable to make it to the inspection
|
General Inspection | 10/29/2014 | 10/29/2014 | 10/29/2014 | | PASS |
Andy J. Long
|
|
|
No activity on pavillion area or next to pond. In process of paving the entrance and park road. Perimeter controls in good condition. No violations observed.
|
General Inspection | 10/9/2014 | 10/9/2014 | 10/9/2014 | | PART |
Andy J. Long
|
|
|
Site perimeter BMPs and existing vegetation buffer is in good condition and containing sediment. No trackout to Mytrle. Work occuring next to pond has effective sediment barier and wattle surrounding the stockpile.
1 correction: 1. Need to re-line the existing washout since the visqueen has become wrinkled and not lining whole pit. Looks like more concrete work for path will occur tomorrow.
Notified Parks n Rec SWPPP manager Toby of the correction. He will work with Western Idaho Construction to make sure they have a lined/contained washout pit for tomorrow's use.
|
General Inspection | 9/24/2014 | 9/24/2014 | 9/24/2014 | | PASS |
Andy J. Long
|
|
|
Parking lot associated with Cancer Pavillion is in progress. Different phases of project are covered under ESC14-00094.
Boise Parks & Rec is managing/updating SWPPP in coordination with contractor.
BMPs installed are DI sediment sacks, perimeter wattles, and construction fencing to delineate the limits of disturbance.
Approved.
|
Site Preparation | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PASS |
Evan Jenkins
|
|
|
Brent Phone #: ###-#### All BMP's in place, Construction Signage Posted No Issues
|
Permit Ready to Issue | | | 6/30/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue & PRINT permit COM | | | 6/30/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 6/5/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 5 2014 11:02AM
|