General Inspection | 4/27/2015 | 4/27/2015 | 4/27/2015 | | PASS |
Evan Jenkins
|
|
|
|
DOC - Permit Finaled | 4/27/2015 | 4/27/2015 | 4/27/2015 | P | PASS |
Evan Jenkins
|
|
|
Complete No ESC issues
|
General Inspection | 3/11/2015 | 3/11/2015 | 3/11/2015 | | PASS |
Andy J. Long
|
|
|
Building shell is complete and loose dirt/sediment is contained within the paved parking lot perimeter. No loose trash or materials, no trackout to Wildwood or Fairview.
Parking lot storm drains have filter bag protection.
Approved.
|
General Inspection | 1/23/2015 | 1/23/2015 | 1/23/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 12/8/2014 | 12/8/2014 | 12/8/2014 | | PASS |
Evan Jenkins
|
|
|
WIP: foundation work currently being conducted. no esc issues at time of inspection
|
General Inspection | 10/16/2014 | 10/16/2014 | 10/16/2014 | | PASS |
Evan Jenkins
|
|
|
|
Issue & PRINT permit COM | | | 10/9/2014 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/30/2014 | | 6/30/2014 | | DONE |
Andy J. Long
|
|
|
ESC site map and narrative submitted and approved.
|
Application received | | | 6/23/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 23 2014 10:33AM
|