Site Final | 1/9/2015 | 1/9/2015 | 1/9/2015 | A | DONE |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 1/9/2015 | 1/9/2015 | 1/9/2015 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 12/9/2014 | 12/9/2014 | 12/9/2014 | | PASS |
Andy J. Long
|
|
|
WIP on Aberdeen 4-plex. Near completion. Landscaping in process of being installed. Colehaven St. has been recently swept; DI bags installed.
|
General Inspection | 10/16/2014 | 10/16/2014 | 10/17/2014 | | PART |
Andy J. Long
|
|
|
Aberdeen 4-plex WIP. No major trackout to surrounding streets, concrete work is currently on hold and old washout is drying out. Storm drains have inlet protection, construction entrance to new phase has been maintained.
Correction:
Need to sweep sidewalks and gutters along Colehaven.
|
Issue & PRINT permit COM | | | 8/28/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 6/24/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 24 2014 6:16PM
|