General Inspection | 5/1/2015 | 5/1/2015 | 5/1/2015 | | PASS |
Evan Jenkins
|
|
|
|
DOC - Permit Finaled | 5/1/2015 | 5/1/2015 | 5/1/2015 | P | PASS |
Evan Jenkins
|
|
|
Project is Complete. ESC Conditions are satisfied w/ no issues/violations
|
General Inspection | 3/16/2015 | 3/16/2015 | 3/16/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 1/27/2015 | 1/27/2015 | 1/27/2015 | | PASS |
Evan Jenkins
|
|
|
Near completion. WIP: no esc issues
|
General Inspection | 12/10/2014 | 12/10/2014 | 12/10/2014 | | PART |
Andy J. Long
|
|
|
Need to suppress stone cutting dust with cooling water or keep with containment tarps that are set up.
Permit is posted, no erosion or sediment trackout. WIP.
|
Random Inspection | 10/1/2014 | 10/1/2014 | 10/1/2014 | P | PASS |
Andy J. Long
|
|
|
One Capitol Center exterior TI is in progress. Permit is posted, BMPs installed and no sediment or nonstormwater discharges observed. No corrections required.
|
Override - Parcel Holds | | | 8/29/2014 | | |
|
|
|
|
Issue & PRINT permit COM | | | 8/29/2014 | | DONE |
|
|
|
|
Application received | | | 7/2/2014 | | |
|
|
|
|
Routing - Erosion and Sediment | 7/2/2014 | | 7/2/2014 | | DONE |
Andy J. Long
|
|
|
ESC plan and SWPPP binder submitted and approved. Valid PD, RP to be designated
|