DOC - Permit Finaled | 9/30/2015 | 9/30/2015 | 9/30/2015 | P | PASS |
Andy J. Long
|
|
|
Foundation and canal bridge phase complete. Vertical work on 119 Grove condos is in progress. Work now inspected under ESC14-00928
|
General Inspection | 8/24/2015 | 8/24/2015 | 8/24/2015 | | PASS |
Evan Jenkins
|
|
|
|
Random Inspection | 7/9/2015 | 7/9/2015 | 7/9/2015 | P | PASS |
Andy J. Long
|
|
|
No trackout or muddy discharges observed at site after significant rain storm yesterday eve. Stockpiles, loose dirt, and other materials has stayed within the curbed area of construction.
|
General Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 | | PASS |
Andy J. Long
|
|
|
Permit sign clearly posted on security fence at entrance. Construction activity remaining confined to building footprint. No trackout to 10th or Grove Street. No fugitive dust or discharges observed. Still working on foundation.
|
Random Inspection | 5/11/2015 | 5/11/2015 | 5/11/2015 | P | PASS |
Andy J. Long
|
|
|
WIP on foundation. Site has small footprint within downtown parcel. Rebuilding MS4 on 10th, so no inlet protection. No trackout or discharges. Permit sign posted. No corrections at this time.
|
Site Preparation | 4/15/2015 | 4/15/2015 | 4/15/2015 | P | PART |
Evan Jenkins
|
|
|
Mike Phone #: ###-####
Construction/grading has already commenced prior to site prep inspection. Contractor to keep sediment off sidewalk (which is closed) and remove Porta-Pot from ACHD's ROW
|
Permit Ready to Issue | | | 4/14/2015 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 4/14/2015 | | DONE |
|
|
|
|
Application received | | | 7/29/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 29 2014 11:27AM
|