General Inspection | 9/15/2015 | 9/15/2015 | 9/15/2015 | | PASS |
Andy J. Long
|
|
|
Project complete, ongoing work on seperate greeenhouse is covered under ESC15 -00412. No sediment trackout, discharges, or fugitive dust at site. This permit finaled.
|
DOC - Permit Finaled | 9/15/2015 | 9/15/2015 | 9/15/2015 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/31/2015 | 7/31/2015 | 7/31/2015 | | PEND |
Evan Jenkins
|
|
|
reveg
|
General Inspection | 6/15/2015 | 6/15/2015 | 6/15/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 4/28/2015 | 4/28/2015 | 4/28/2015 | | PASS |
Andy J. Long
|
|
|
Simplot Plant Science project is near completion. Green house building and stormwater swale have been completed.
There is a large stockpile on the south side of the site that will need stabilization or removal as well as stabilizing the disturbed dirt behind adjacent to the new structures.
No trackout to Phillipi or Irving. Greenbelt path connection has been swept and the strip between fence and path now has grasses and weeds hold sediment in place.
No corrections.
|
General Inspection | 3/11/2015 | 3/11/2015 | 3/11/2015 | | PASS |
Andy J. Long
|
|
|
WIP at Simplot Plant Science compound.
Entrance off Phillipi has been closed. Landscaping is in progress. Need to finish stabilization of the area next to Greenbelt path extension and a final sweeping of surrounding hard sufaces. No trackout or non-stormwater discharges.
Will continue to monitor for stabilization/revegetation.
|
General Inspection | 1/22/2015 | 1/22/2015 | 1/22/2015 | | PASS |
Evan Jenkins
|
|
|
|
Permit Ready to Issue | | | 11/14/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue & PRINT permit COM | | | 11/14/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Routing - Erosion and Sediment | 8/11/2014 | | 8/11/2014 | | DONE |
Andy J. Long
|
|
|
ESC site map and narrative submitted. Valid Plan Designer, Responsible person to be designated.
|
Application received | | | 8/6/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 6 2014 4:43PM
|