General Inspection | 12/8/2015 | 12/8/2015 | 12/9/2015 | | DONE |
Evan Jenkins
|
|
|
|
DOC - Permit Finaled | 12/9/2015 | 12/9/2015 | 12/9/2015 | P | PASS |
Evan Jenkins
|
|
|
Complete ESC conditions satisfied
|
General Inspection | 11/23/2015 | 11/23/2015 | 11/23/2015 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/6/2015 | 11/6/2015 | 11/6/2015 | | PEND |
Evan Jenkins
|
|
|
perm re-veg
|
General Inspection | 10/22/2015 | 10/22/2015 | 10/22/2015 | | PEND |
Evan Jenkins
|
|
|
Construction Complete Remove Temp BMP's (straw waddles and DI protection
|
General Inspection | 10/7/2015 | 10/7/2015 | 10/7/2015 | | PEND |
Evan Jenkins
|
|
|
80% re-vegetation nearly established. Pending for 80%. Rest of permits are finaled out at this time.
|
General Inspection | 9/22/2015 | 9/22/2015 | 9/22/2015 | | PEND |
Evan Jenkins
|
|
|
waiting for 80% perm re-veg to become established. BLD is finaled
|
General Inspection | 9/7/2015 | 9/7/2015 | 9/8/2015 | | CANC |
Andy J. Long
|
|
|
holiday
|
General Inspection | 8/21/2015 | 8/21/2015 | 8/21/2015 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/6/2015 | 8/6/2015 | 8/6/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: on exterior. pending re-vegetation of disturbed areas. Perimeter BMP's still in place along with downslope Drop Inlet Protection. No Issues observed
|
General Inspection | 7/22/2015 | 7/22/2015 | 7/22/2015 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/7/2015 | 7/7/2015 | 7/7/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: still commencing. no ESC issues observed at this time
|
Site Preparation | 6/19/2015 | 6/22/2015 | 6/22/2015 | P | PASS |
Andy J. Long
|
|
|
WIP on large foothills home. No more excavation, interior and exterior finishes remain including landscaping. No sediment leaving site, hillside vegetation has been preserved around limits of disturbance. Approved.
|
General Inspection | 6/19/2015 | 6/19/2015 | 6/19/2015 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/4/2015 | 6/4/2015 | 6/4/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: BMP's and Permit still posted. No ESC issues at this time
|
General Inspection | 5/19/2015 | 5/20/2015 | 5/20/2015 | P | PASS |
Evan Jenkins
|
|
|
WIP: on exterior of SFH. BMP's still in place, with no ESC issues at time of inspection
|
General Inspection | 5/19/2015 | 5/19/2015 | 5/19/2015 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 5/1/2015 | 5/1/2015 | 5/4/2015 | | PASS |
Evan Jenkins
|
|
|
No issues at this time
|
General Inspection | 4/16/2015 | 4/16/2015 | 4/16/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 4/1/2015 | 4/1/2015 | 4/1/2015 | | PASS |
Evan Jenkins
|
|
|
Home near completion. No ESC issues at this time. Perminant Re-vegetation needs to occur prior to ESC permit being finaled out
|
General Inspection | 3/13/2015 | 3/13/2015 | 3/13/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: no esc issues at this time
|
General Inspection | 2/20/2015 | 2/26/2015 | 2/26/2015 | A | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 2/19/2015 | 2/19/2015 | 2/20/2015 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 2/2/2015 | 2/2/2015 | 2/2/2015 | | PASS |
Evan Jenkins
|
|
|
|
Site Preparation | 10/1/2014 | 10/2/2014 | 10/2/2014 | A | PASS |
Evan Jenkins
|
|
|
Ken Phone #: ###-#### Permit Posted next to Construction Entrance. Lined Concrete Washout installed along with perimeter BMP's installed. Drop Inlet located below site is also protected with a witches hat. Good looking Site. lot is flat for a Hillside lot
|
Permit Ready to Issue | | | 10/1/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue & PRINT permit SFD | | | 10/1/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 8/13/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 13 2014 10:14AM
|