DOC - Permit Finaled | 4/28/2015 | 4/28/2015 | 4/28/2015 | P | PASS |
Andy J. Long
|
|
|
|
Site Final | 4/28/2015 | 4/28/2015 | 4/28/2015 | P | PASS |
Andy J. Long
|
|
|
Project complete. Vertical construction and parking lot/site improvements complete. Disturbed area has been hydroseeded. ESC permit conditions satisfied, all other permits finaled.
|
General Inspection | 3/24/2015 | 3/24/2015 | 3/24/2015 | | PASS |
Andy J. Long
|
|
|
Warehouse addition near complete as well as new curbing. Landscaping and placement of irrigation lines is in progress. No trackout or muddy runoff. Approved.
|
General Inspection | 2/3/2015 | 2/3/2015 | 2/3/2015 | | PASS |
Andy J. Long
|
|
|
WIP on building addition. The construction area is below the grade of Eagleson. No runoff from site observed; no trackout. Approved.
|
Issue & PRINT permit COM | | | 10/20/2014 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 8/18/2014 | | 8/18/2014 | | DONE |
Andy J. Long
|
|
|
SWPPP and ESC site plan approved. RP to be designated.
|
Application received | | | 8/14/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 14 2014 2:38PM
|