General Inspection | 6/16/2015 | 6/16/2015 | 6/16/2015 | | PASS |
Evan Jenkins
|
|
|
|
DOC - Permit Finaled | 6/16/2015 | 6/16/2015 | 6/16/2015 | A | PASS |
Evan Jenkins
|
|
|
Vegetation Re-established ESC Conditions Satisfied
|
General Inspection | 6/1/2015 | 6/1/2015 | 6/1/2015 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 5/15/2015 | 5/15/2015 | 5/15/2015 | | PASS |
Andy J. Long
|
|
|
Vegetation on the shoulders of path has established and path has been open to public for some time. Some temp wattles are still installed drainage and culvert structures. Permit should be ready to close next inspection and assess whether BMPs may remain or be removed.
Checked discharge from Council Springs Creek into the Boise River by the Eckart bridge (creek channel passess through construction site) during rain event and it clear and not turbid.
|
General Inspection | 4/30/2015 | 4/30/2015 | 4/30/2015 | | PASS |
Andy J. Long
|
|
|
Greenbelt path complete and in use. Shoulders have been hydroseeded and vegetation is still establishing. Next inspection will check to see if disturbed areas are stabilized and temp BMPs may be removed.
|
General Inspection | 4/15/2015 | 4/15/2015 | 4/15/2015 | | PASS |
Evan Jenkins
|
|
|
Minimal Vegetation Growth. It appears to be volunteer growth, not from the hydroseeding. No ESC issues at this time
|
General Inspection | 3/27/2015 | 3/27/2015 | 3/27/2015 | | PASS |
Andy J. Long
|
|
|
Construction complete on Eckert Greenbelt path. The shoulders/disturbed area has been hydoseeded but is not established yet. Will continue to monitor. No corrections at this time.
|
Aging Inspection | 2/19/2015 | 2/19/2015 | 2/23/2015 | | PASS |
Andy J. Long
|
|
|
Greenbelt Path is complete and open to public. Shoulders have not yet been seeded or stablized. No flow through Council Springs Creek culverts currently. No trackout, dust issues, or turbid discharges. Need to check on plans for revegetation.
|
Random Inspection | 12/19/2014 | 12/19/2014 | 12/19/2014 | A | PASS |
Andy J. Long
|
|
|
Greenbelt expansion path has been completed, including culvert installation for the two Council Springs Creek road crossings.
Final grading is in progress and the bare ground has not yet been hydroseeded or tacified. No major trackout. No water running in creek currently. Minimal activity at time of inspection.
|
General Inspection | 10/15/2014 | 10/15/2014 | 10/15/2014 | P | PASS |
Andy J. Long
|
|
|
Eckert path is in progress. Council Springs creek crossings have perimeter protection and gravel bags to trap sediment at outlet. No erosion issues.
Yesterday observed several spots where cement trucks washed out without containment. Called project manager/coordinator Jeff and requested that washout be conducted in a designated area. Knife River stated they will have trucks washout at DH #12 facility. Today no new washouts observed/no acitivity. Will continue to monitor.
|
BMP Violation | 9/26/2014 | 9/26/2014 | 9/26/2014 | A | PASS |
Andy J. Long
|
|
|
Corrections at Eckart Greenbelt path have been completed.
1. Additional wattles have been installed at the south channel/culvert of Council Springs Creek to prevent sediment runoff from running into the stream. 2. Gravel bags have been laid flat on culvert inlets to create filter and settling time for sediment.
3. Gravel bag put at the inlet of the north culvert near Lucky Harris construction entrance.
Other: Water truck was onsite to keep down dust. The two channels may be diverted so that when the path crosses the creek they can stop flow.
Approved.
|
Site Preparation | 9/24/2014 | 9/25/2014 | 9/25/2014 | A | PART |
Andy J. Long
|
|
|
Eckart Greenbelt Path
Permit posted, SWPPP/NOI # onsite (no updates or inspection reports included), no dust issues or trackout to Eckart at time of inspection.
Note: No site prep inspection to inspect BMPs was requested as required.
Corrections:
1. Properly stake in loose wattles that are installed. 2. No inlet protection as indicated on site map for the culvert conveying the north channel of Council Springs Creek. 3. Unprotected and disturbed banks along the south channel crossing of of Council Springs Creek . 150-200 meters away from outlet to Boise River.
Notified Jeff at Knife River of issue as well as Syman Company of the problem and requested corrections. Rain forecasted for this weekend so requested corrections before weekend.
|
Application received | | | 9/12/2014 | | |
|
|
|
per Jason Taylor and Josh Johnson no additional permits required
|
Routing - Erosion and Sediment | 9/12/2014 | | 9/12/2014 | | DONE |
Evan Jenkins
|
|
|
Site Prep Inspection Required Prior to Any Earth Disturbance
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/12/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 9/12/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 9/12/2014 | | DONE |
Candy A. Nichols
|
|
|
called Jeff to let know permit is ready and how much is owed
|
Issue & PRINT permit COM | | | 9/12/2014 | | DONE |
Candy A. Nichols
|
|
|
|