General Inspection | 6/15/2015 | 6/15/2015 | 6/15/2015 | | PASS |
Evan Jenkins
|
|
|
|
DOC - Permit Finaled | 6/15/2015 | 6/15/2015 | 6/15/2015 | P | PASS |
Evan Jenkins
|
|
|
Project Complete ESC Conditions Satisfied
|
General Inspection | 4/29/2015 | 4/29/2015 | 4/29/2015 | | PASS |
Andy J. Long
|
|
|
Well treatment plant is in progress. Well building is mostly complete. Grounds and parking area are still undeveloped. Construction rock is placed at the entrance to prevent trackout.
No discharges or sediment leaving site. Materials and waste is contained, no dust or other issues. No corrections needed at this time.
|
Aging Inspection | 3/10/2015 | 3/10/2015 | 3/10/2015 | | PASS |
Andy J. Long
|
|
|
WIP. Water treatment and filter station walls are constructed. No trackout to Fisk or loose sediment leaving site. No MS4 system on Fisk, but sheet flow goes to Fairview inlets. The canal is protected and currently not flowing.
No corrections.
|
(F) Reprint permit | | | 11/13/2014 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 9/25/2014 | | DONE |
|
|
|
|
Application received | | | 9/22/2014 | | |
|
|
|
|
Routing - Erosion and Sediment | 9/22/2014 | | 9/22/2014 | | DONE |
Andy J. Long
|
|
|
ESC plan and site map submitted and approved. Valid PD and RP provided; this ESC permit can be used for the demolition and new construction phases of the project.
|