Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberESC14-00929
StatusFinaled
Name BURKE WILLIAMS
Site Address 220 W GOWEN RD
Project Name 
Customer Number 
ePlanReviewNo
Description
Utlity trenching/ project is off of Gowen/Production Ave, 3/4 mile North on Production Ave. from Gowen.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled12/1/201412/1/201412/1/2014PPASS
DetailsAndy J. Long
Pipeline project on eastern edge of airport area is complete and site returned to preexisting condtions. Temp BMPs have been removed and construction complete.
Random Inspection10/21/201410/21/201410/21/2014PPASS
DetailsAndy J. Long
Utility trenching project by Earth Energy along Production street is in progress. No trackout or other ESC violations. WIP. Permit is posted.
Site Preparation9/30/20149/30/20149/30/2014PPASS
DetailsAndy J. Long
Earth Energy on site making preparations for utility project. No MS4 or surface waters in project area. Drainage flows to airport's perimeter berm & swale. Approved.
Routing - Erosion and Sediment9/29/2014 9/29/2014 DONE
DetailsEvan Jenkins
Project mainly in ACHD ROW. Very little disturbance within the City's Jurisdiction. Contractor to follow ESC Permit Conditions/Requirements at all times
PLANS/APPL TAKEN TO FRONT DESK  9/29/2014  
Permit Ready to Issue  9/29/2014 DONE
DetailsCandy A. Nichols
Telephone call  9/29/2014 DONE
DetailsCandy A. Nichols
called Burke to let know permit is ready-left message on his phone (###-####)
Issue & PRINT permit COM  9/29/2014 DONE
Application received  9/26/2014