DOC - Permit Finaled | 2/9/2015 | 2/9/2015 | 2/9/2015 | P | PASS |
Andy J. Long
|
|
|
Building has been demolished and site has been cleaned with all construction debris removed. The site has been graded flat and is a pit run/sandy river material. No vegetation requested due to site being location of further park construction activities in near feature
Currently the area has restricted vehicle access with large boulders and locked gate, but the porta-pot service truck (river park portapots - not construction related) has made the road muddy and also crosses the Greenbelt path to access a restroom.
|
General Inspection | 2/6/2015 | 2/9/2015 | 2/9/2015 | A | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/6/2015 | 2/6/2015 | 2/6/2015 | P | PASS |
Andy J. Long
|
|
|
|
Permit Ready to Issue | | | 10/21/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue & PRINT permit COM | | | 10/21/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Routing - Erosion and Sediment | 10/2/2014 | | 10/2/2014 | | PASS |
Andy J. Long
|
|
|
ESC plan with narrative and site map submitted and approved. Valid RP and PD designated. Site prep inspection/notification of project start is REQUIRED.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/2014 | | DONE |
|
|
|
|
Application received | | | 9/30/2014 | | |
|
|
|
|
Routing - Erosion and Sediment | 9/30/2014 | | 9/30/2014 | | FAIL |
Evan Jenkins
|
|
|
Due to Scope of Demo, Location in Env. Sensitive Area and Size of Project, Full ESC Narrative and Site Maps Required.
ESC Waiver Denied
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/30/2014 | | |
|
|
|
|