Site Final | 4/8/2015 | 4/8/2015 | 4/8/2015 | P | PASS |
Andy J. Long
|
|
|
Check to see if inlet bag is still installed...
All temporary BMPs have been removed and site has been cleaned and stabilized. ESC permit conditions satisfied & permit finaled.
|
DOC - Permit Finaled | 4/8/2015 | 4/8/2015 | 4/8/2015 | P | PASS |
Andy J. Long
|
|
|
|
Random Inspection | 3/6/2015 | 3/6/2015 | 3/6/2015 | A | PASS |
Andy J. Long
|
|
|
Airport sign and landscaping project is complete. Requested that Diamond Contractors remove the sediment bag when they pick up the rest of their equipment and request a site final.
No loose sediment, uncontained materials, or other issues.
|
Site Preparation | 10/21/2014 | 10/21/2014 | 10/21/2014 | P | PASS |
Andy J. Long
|
|
|
Work has started at Airport landscaping project. Permit is posted, DI's have inlet protection. No trackout or sediment runoff.
No corrections at this time.
|
Issue & PRINT permit COM | | | 10/14/2014 | | DONE |
Candy A. Nichols
|
|
|
|
(F) Reprint permit | | | 10/14/2014 | | DONE |
Candy A. Nichols
|
|
|
|
(F) Reprint permit | | | 10/14/2014 | | DONE |
|
|
|
|
Application received | | | 10/9/2014 | | |
|
|
|
|
Routing - Erosion and Sediment | 10/9/2014 | | 10/9/2014 | | PASS |
Andy J. Long
|
|
|
ESC plan with site map and narrative submitted and approved. Valid RP and PD designated.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/9/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/9/2014 | | DONE |
|
|
|
|
Telephone call | | | 10/9/2014 | | DONE |
|
|
|
called Chris Sheppard and left a voicemail that permit is ready to be picked up
|