Aging Inspection | 9/30/2015 | 9/30/2015 | 9/30/2015 | | PASS |
Andy J. Long
|
|
|
SFH complete. ESC permit conditions satisfied
|
DOC - Permit Finaled | 9/30/2015 | 9/30/2015 | 9/30/2015 | P | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 7/31/2015 | 7/31/2015 | 7/31/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: No ESC issues at this time. Stockpiles surrounding the house, with very little chance of discharging offsite
|
Site Preparation | 3/10/2015 | 3/11/2015 | 3/11/2015 | A | CANC |
Andy J. Long
|
|
|
Luke Phone #: ###-####
Site preparation inspected Tuesday 3/10 and passed
|
Telephone call | | | 3/11/2015 | | DONE |
Candy A. Nichols
|
|
|
called Steve to let know there is no ESC yellow card on site and he needs to come in as soon as possible to get the card and post at jobstie-left message on his phone
|
Site Preparation | 3/10/2015 | 3/10/2015 | 3/10/2015 | P | PASS |
Andy J. Long
|
|
|
Site prep requested by Luke from Syringa
Meet RP on site. BMPs include perimeter straw wattle and preservation of existing grass and trees.
Parcel has Crane Creek running diagonal across lot, the Creek is lined with sandstone bricks and covered by concrete slab. Sandstone channel and slab are to be undisturbed and left as is. To keep vehicles and any stockpiling off the unsupported slab a silt fence will be installed on either side of creek. The house will be west of channel, and the detached garage to the east off the ally.
Permit onsite. BMPs installed. DI on Dewey is clogged with leaves and debris unrelated to construction.
|
Override - Parcel Holds | 3/10/2015 | 1/1/1900 | 3/10/2015 | | |
|
|
|
ESC Site Prep
|
Override - Parcel Holds | | | 3/10/2015 | | |
|
|
|
|
Issue & PRINT permit SFD | | | 3/10/2015 | | DONE |
|
|
|
|
Application received | | | 2/18/2015 | | |
|
|
|
|