Site Final | 8/6/2015 | 8/6/2015 | 8/6/2015 | A | PASS |
Andy J. Long
|
|
|
4-plex at west end of newest Aberdeen phase (Winston & Fry) is complete. All permits finaled. Landscaping complete. Dumpsters removed. WIP on east end of phase.
|
General Inspection | 8/5/2015 | 8/5/2015 | 8/5/2015 | | PASS |
Andy J. Long
|
|
|
|
Site Preparation | 4/21/2015 | 4/21/2015 | 4/21/2015 | P | FAIL |
Mike Jordan
|
|
|
Needs to provide ESC permit sign, Also existing concrete washout full. Contractor noted that they will be removing the existing washout and placing another in different area.
|
Permit Ready to Issue | | | 4/17/2015 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 4/17/2015 | | DONE |
|
|
|
|
Application received | | | 2/25/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 25 2015 12:27PM
|