Aging Inspection | 7/24/2015 | 7/24/2015 | 7/24/2015 | | PASS |
Andy J. Long
|
|
|
Building demolished, all materials removed and swept. Canal bank undisturbed, concrete building pad left on site as stabilization. ESC permit finaled.
|
DOC - Permit Finaled | 7/24/2015 | 7/24/2015 | 7/24/2015 | P | PASS |
Andy J. Long
|
|
|
|
Permit Ready to Issue | | | 3/5/2015 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 3/5/2015 | | DONE |
|
|
|
|
Application received | | | 3/4/2015 | | |
|
|
|
|
Routing - Erosion and Sediment | 3/4/2015 | | 3/4/2015 | | DONE |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED)
Removal of Structure Only: All concrete and associated with the foundations/footings will be left in place for future use. Approx 1,500sq ft'. Project is backed up right onto the canal. Environmentally Sensitive
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/4/2015 | | |
|
|
|
|