General Inspection | 6/29/2016 | 6/29/2016 | 6/29/2016 | P | DONE |
Evan Jenkins
|
|
|
|
DOC - Permit Finaled | 6/29/2016 | 6/29/2016 | 6/29/2016 | P | PASS |
Evan Jenkins
|
|
|
Carwash is complete and in operation. No ESC Issues Observed ESC Conditions Satisfied
|
General Inspection | 5/30/2016 | 5/30/2016 | 5/30/2016 | | CANC |
Evan Jenkins
|
|
|
Holiday
|
Site Final | 4/14/2016 | 4/14/2016 | 4/15/2016 | P | NR |
Andy J. Long
|
|
|
Need to stabilize disturbed shoulder area and sweep bike lane...
No sediment leaving site, all other permits finaled.
|
General Inspection | 4/8/2016 | 4/8/2016 | 4/8/2016 | | PEND |
Evan Jenkins
|
|
|
minor landscaping needs to be complete. carwash is up and running
|
General Inspection | 2/22/2016 | 2/22/2016 | 2/22/2016 | | CANC |
Evan Jenkins
|
|
|
|
General Inspection | 1/5/2016 | 1/5/2016 | 1/5/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/20/2015 | 11/20/2015 | 11/20/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: No discharges leaving the site onto fairview or cloverdale. no ESC issues observed
|
General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 | P | PASS |
Andy J. Long
|
|
|
WIP at Rocket Expresss Washout. No trackout to Cloverdale or Fairview. Site is utilizing staging area for material containment and concrete washout pit. Water truck is on site to help with dust and compaction. Approved.
|
Site Preparation | 8/26/2015 | 8/26/2015 | 8/26/2015 | P | PASS |
Andy J. Long
|
|
|
Rocket Wash carwash is in progress. Building structure is erect, but site has to be built up. Permint sign and SWPPP info located at construciton entrance on Cloverdale. No trackout or discharges, no water truck seen on site, but no fugitive dust issues observed and no complaints have been received. Site has restricted access on Fairview with no dirt or trackout able to leave site to the north. Lined concrete washout pit has been utilized for the work.
Approved.
|
Site Preparation | 6/11/2015 | 6/12/2015 | 6/12/2015 | A | PASS |
Evan Jenkins
|
|
|
Brent Phone #: ###-####
Permit posted next to construction entrance on Cloverdale. Contractor to get a water truck onsite to keep dust down throughout construction Approved for construction at this time
|
Permit Ready to Issue | | | 6/11/2015 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 6/11/2015 | | DONE |
|
|
|
|
Application received | | | 3/12/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 12 2015 11:33PM
|