Site Final | 10/13/2015 | 10/13/2015 | 10/13/2015 | P | PASS |
Andy J. Long
|
|
|
Townhome complete. Materials staged in access alley have been swept and cleaned. All work on east side (7 townhomes) of Hope Ridge is complete. Interior work ongoing on west side of block and ESC permits open. ESC permit finaled.
|
Aging Inspection | 9/16/2015 | 9/16/2015 | 9/16/2015 | | CANC |
Evan Jenkins
|
|
|
|
Site Preparation | 4/8/2015 | 4/14/2015 | 4/14/2015 | A | PASS |
Andy J. Long
|
|
|
Gary Phone #: ###-####
Bella Vista townhome project on Malad Street. 14 townhomes, 7 on each side of the newly developed square/block.
ESC permit issued for each BLD permit per townhome.
BMPs include permit signage, DI protection on subdivision storm drain and new inlet on Malad (west) of construction. Concrete washout pit has been excavated. RP Gary will line with visqueen on Wednesday. Concrete work will be Thursday or Friday.
The project will be phased - 7 homes on the east side will have their foundations started. Once in progress, the 7 townhomes
Discussed other BMPs that will be necessary including trash enclosures, trackout sweep up, and having workers park on paved surfaces.
Approved to start relocate misplaced sewer stub line. Subdivision ESC permit is ESC14-00892
|
Issue & PRINT permit SFD | | | 4/7/2015 | | DONE |
|
|
|
|
Application received | | | 3/16/2015 | | |
|
|
|
|