General Inspection | 9/26/2016 | 9/30/2016 | 9/29/2016 | A | CANC |
Andy J. Long
|
|
|
Project finaled 9/28
|
Site Final | 9/28/2016 | 9/28/2016 | 9/28/2016 | P | PASS |
Andy J. Long
|
|
|
Cordillera #2 subdivison and 6-plex construction is complete. Landscaping and irrigation installed. No remaining temp BMPs in municipal storm drain.
Private storm drains within site and final sweeping of landscaping gravel to be completed by the apartment management company. Units now occupied. No construction materials or stockpiles on site.
All permits finaled.
|
General Inspection | 9/26/2016 | 9/26/2016 | 9/26/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 8/9/2016 | 8/9/2016 | 8/9/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/24/2016 | 6/24/2016 | 6/24/2016 | P | PASS |
Evan Jenkins
|
|
|
No issues observed at this time
|
General Inspection | 5/30/2016 | 5/30/2016 | 5/30/2016 | | CANC |
Evan Jenkins
|
|
|
Holiday
|
General Inspection | 4/12/2016 | 4/12/2016 | 4/12/2016 | | PASS |
Andy J. Long
|
|
|
WIP on last building of Cordillera #2. Stormwater from area of construction drains to onsite DIs with sediment filter bags installed.
No trackout to Five Mile, no windblown trash or materials leaving project area.
Will need to do final sweep up and removal of temp BMPs to get ESC final.
Note: Andersen Construction no longer on job, now Summit Development. .
|
General Inspection | 2/26/2016 | 2/26/2016 | 2/26/2016 | | PEND |
Evan Jenkins
|
|
|
more street sweeping needs to occur and temp bmp removal
|
General Inspection | 1/11/2016 | 1/11/2016 | 1/12/2016 | | FAIL |
Andy J. Long
|
|
|
Loose dirt and trackout all over parking and access road through Cordillera #2. Trash and litter is also uncontained in the parking lot area.
DI bag installed in Cordillera #1 is full and needs to be replaced as it still receives drainage from phase 2.
Needs sweeping and trash clean ASAP. Sweep up trackout to bike lane on Five Mile.
|
General Inspection | 11/24/2015 | 11/24/2015 | 11/27/2015 | | PASS |
Andy J. Long
|
|
|
WIP on phase #2 townhomes (7) at Cordillera. Stormwater infrastructure installed and is retained on site. Private stormdrains have sediment bags installed.
Landscaping and irrigation installation in progress, with some loose dirt with construction area. Currently frozen, will need to be swept as work is resumed and completed. No trackout or dishcarges observed.
|
General Inspection | 10/8/2015 | 10/8/2015 | 10/8/2015 | | PASS |
Andy J. Long
|
|
|
WIP on 4-plex foundations at Cordillera #2. Parking lot and utilities already installed. No trackout or discharges offsite. No material spills on parking lot observed. Trash contained. No corrections at this time.
|
Aging Inspection | 8/21/2015 | 8/21/2015 | 8/21/2015 | | PASS |
Andy J. Long
|
|
|
Parking/access road are complete as well as sidewalks, gutters and stormdrains. No vertical construction. No discharges or trackout. Approved.
|
Random Inspection | 5/19/2015 | 5/19/2015 | 5/19/2015 | P | PASS |
Andy J. Long
|
|
|
WIP on Cordillera #2. No trackout to Fivemile or discharges offsite. BMPs installed. No corrections.
|
Site Preparation | 3/30/2015 | 3/31/2015 | 3/31/2015 | A | PASS |
Evan Jenkins
|
|
|
Permit Posted, Straw waddles are almost installed completely. Ken will be getting a water truck to keep onsite to keep fugitive dust to a minimum. SWO removed. Clear to begin work.
|
Stop Work Order | 3/31/2015 | 3/31/2015 | 3/31/2015 | A | PASS |
Evan Jenkins
|
|
|
Mass Grading occured prior to issuence of permits. This occured on 3-25-15. Site prep inspection shedualed for 3-31-15
|
Routing - Erosion and Sediment | 3/25/2015 | | 3/26/2015 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION IS REQUIRED PRIOR TO ANY MORE EARTH DISTURBANCE, OR ANOTHER SWO SHALL BE ISSUED) ALL BMP'S MUST BE IN PLACE PRIOR TO SITE PREP INSEPCTION, ALONG WITH YELLOW PERMIT CARD POSTED.
Constists of 7 Residential Apartment Buildings, 6 two-story townhouses, site improvements. Sewer & water mains, stormwater infrastructures, irrigation, concrete curbs, roads and landscaping
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2015 | | |
|
|
|
|
Telephone call | | | 3/26/2015 | | DONE |
Christina Prado
|
|
|
called Dave to advise permit is ready for issuance
|
Permit Ready to Issue | | | 3/26/2015 | | DONE |
Christina Prado
|
|
|
|
Issue & PRINT permit COM | | | 3/26/2015 | | DONE |
|
|
|
|
Application received | | | 3/25/2015 | | |
|
|
|
|