General Inspection | 11/12/2015 | 11/12/2015 | 11/12/2015 | | PASS |
Andy J. Long
|
|
|
4-plex building construction complete and parking lot area has been swept and waste material removed.
Carports and open space landscaping covered under Breckenwood main permit ESC14-01040. This permit finaled.
|
DOC - Permit Finaled | 11/12/2015 | 11/12/2015 | 11/12/2015 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/28/2015 | 10/28/2015 | 10/28/2015 | | PASS |
Andy J. Long
|
|
|
WIP on interiors of 4-plexes. No sediment leaving site, though the interior parking lot will need thorough sweeping upon completion and striping. No discharges offsite.
|
General Inspection | 10/9/2015 | 10/9/2015 | 10/9/2015 | | PASS |
Andy J. Long
|
|
|
WIP at Breckenridge 4-plexes on vertical construction, interior wood work, and painting. No trackout or loose sediment being carried offsite. Boundary next to Maple Grove is bermed and has chain link fence. No violations observed.
|
General Inspection | 9/23/2015 | 9/23/2015 | 9/23/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: on interior. No ESC issues observed
|
Permit Ready to Issue | | | 5/29/2015 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 5/29/2015 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/8/2015 | | 4/8/2015 | | DONE |
Andy J. Long
|
|
|
SWPPP narrative and map for Breckenwood subdivision 4-plexes resubmitted with revisions to show 9 units. Subdivision BMPs implemented under ESC14-01040
|
Application received | | | 4/3/2015 | | |
|
|
|
|