DOC - Permit Finaled | 10/19/2016 | 10/19/2016 | 10/19/2016 | P | PASS |
Andy J. Long
|
|
|
No further ESC inspections until Terra Nativa slide investigation and mitigation is complete. Alto Via Ct. is closed.
|
General Inspection | 10/19/2016 | 10/19/2016 | 10/19/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/4/2016 | 10/4/2016 | 10/4/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/19/2016 | 9/19/2016 | 9/19/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/2/2016 | 9/2/2016 | 9/2/2016 | | CANC |
Evan Jenkins
|
|
|
area has been condemed
|
General Inspection | 8/18/2016 | 8/18/2016 | 8/18/2016 | | PEND |
Andy J. Long
|
|
|
No inspection
|
General Inspection | 8/3/2016 | 8/3/2016 | 8/3/2016 | | CANC |
Andy J. Long
|
|
|
Alto Via still under investigation and is closed
|
General Inspection | 7/19/2016 | 7/19/2016 | 7/19/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/4/2016 | 7/4/2016 | 7/4/2016 | | CANC |
Evan Jenkins
|
|
|
holiday
|
General Inspection | 6/17/2016 | 6/17/2016 | 6/17/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/2/2016 | 6/2/2016 | 6/3/2016 | | CANC |
Evan Jenkins
|
|
|
|
General Inspection | 5/18/2016 | 5/18/2016 | 5/18/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/3/2016 | 5/3/2016 | 5/3/2016 | | CANC |
Andy J. Long
|
|
|
|
(F) Reprint permit | | | 4/20/2016 | | DONE |
|
|
|
|
General Inspection | 4/18/2016 | 4/18/2016 | 4/18/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/1/2016 | 4/1/2016 | 4/1/2016 | | PASS |
Andy J. Long
|
|
|
WIP on interior. No significant trackout. Front bank vegetation has been preserved and fiber wattle is installed at sidewalk. DI bag in MS4. No corrections at this time. Should be done by end of month
|
General Inspection | 3/17/2016 | 3/17/2016 | 3/17/2016 | | PASS |
Andy J. Long
|
|
|
No trackout. No discharges. Trackout from last week was cleaned up and new rock installed on construction entrance. Front slope vegetation was preserved and perimeter wattle installed as well as DI sediment bag. Approved.
|
General Inspection | 3/2/2016 | 3/2/2016 | 3/4/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 2/16/2016 | 2/16/2016 | 2/16/2016 | | PASS |
Andy J. Long
|
|
|
|
Tracking Control | 2/1/2016 | 2/1/2016 | 2/1/2016 | P | PASS |
Andy J. Long
|
|
|
Report of trackout and damage done to lots on Alto Via.
Inspected this site, the only active site on Alto Via and there are no violations.BMPs installed .
Trackout is no longer significant on street, but some cookies and mud bogging was done on an open stretch and trash and litter at the end of the culdesac. Appears to be the work of joy-riders...
|
General Inspection | 1/26/2016 | 1/26/2016 | 1/26/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 1/8/2016 | 1/11/2016 | 1/12/2016 | A | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 1/7/2016 | 1/7/2016 | 1/8/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 12/23/2015 | 12/23/2015 | 12/23/2015 | | CANC |
Andy J. Long
|
|
|
|
Tracking Control | 11/27/2015 | 12/8/2015 | 12/10/2015 | A | PART |
Andy J. Long
|
|
|
check track out
Trackout tracks into street cleaned. Some residual mud and dirt on sidewalk and gutter. Workers stayed off entrance today during the wet weather.
Need to conduct housekeeping and maintain DI bag as conditions dry out.
|
General Inspection | 11/27/2015 | 11/27/2015 | 11/27/2015 | | PART |
Bill VanDegrift
|
|
|
called rp about track out and left a message, set up reinspection
|
General Inspection | 11/12/2015 | 11/12/2015 | 11/12/2015 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/28/2015 | 10/28/2015 | 10/28/2015 | | PASS |
Andy J. Long
|
|
|
WIP. Road has been swept and construction entrance improved since last week's storm. No new corrections. RP-GC alerted ESC divisions of issues and corrections last week.
|
General Inspection | 10/12/2015 | 10/12/2015 | 10/12/2015 | A | PASS |
Andy J. Long
|
|
|
WIP on initial phases of framing. Foundation is complete. No trackout or discharges coming from site. Edge of sidewalk and toe of front slope has fiber wattles installed properly for perimter sediment control and hillside vegetation has been preserved where possible. No corrections at this time.
|
General Inspection | 9/10/2015 | 9/10/2015 | 9/10/2015 | P | PART |
Andy J. Long
|
|
|
Project started without site preparation inspection. No permit sign posted.
Wattle installed at toe of slope and surrounding hillside vegetation has been preserved. No significant issues but Bruno Built needs to schedule site preparation inspections on all foothills homes.
|
Permit Ready to Issue | | | 7/22/2015 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 7/22/2015 | | DONE |
|
|
|
|
Application received | | | 4/13/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 13 2015 11:53AM
|