Site Final | 12/14/2015 | 12/14/2015 | 12/14/2015 | P | PASS |
Andy J. Long
|
|
|
Home complete and is now landscaped and stabilized with bark mulch. Street, sidewalk and gutter in front of home are clean.
Temp BMP removal (DI bags) will be completed under main Mill District Square permit ESC11-00525. This permit finaled.
|
Aging Inspection | 10/30/2015 | 10/30/2015 | 10/30/2015 | | PASS |
Andy J. Long
|
|
|
WIP on interior and need to finish landscaping. Adjacent lot is only open lot on Woodcutter and will need cleaning if new SFH does not start. No issues in Mill District Square. No sediment runoff, workers staying off muddy areas.
|
Site Preparation | 5/21/2015 | 5/21/2015 | 5/21/2015 | P | PART |
Andy J. Long
|
|
|
###-#### Inspection requested via web by Erby Gonzales
Ready for excavation. Permit sign is posted on back of Brighton sign.
Correction:
Empty out and reinstall DI bag on Sawmill and Woodcarver by end of week. It is full
Correction issued to Erbie who was onsite in Mill District Square
|
Permit Ready to Issue | | | 5/19/2015 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 5/19/2015 | | DONE |
|
|
|
|
Application received | | | 5/1/2015 | | |
|
|
|
|