Site Final | 1/31/2019 | 2/1/2019 | 2/1/2019 | P | PASS |
Andy J. Long
|
|
|
All temporary storm drain sediment protection has been removed as requested. All parcels complete. No construciton activity or disturbed area. ESC permit conditions satisfied.
|
General Inspection | 1/22/2019 | 1/22/2019 | 1/22/2019 | P | PEND |
Andy J. Long
|
|
|
Correction request to BlackRock Homes to remove all remaining DI bags in subdivision storm drains - Highland Valley, Taboo, Hakassan and Tao.
|
General Inspection | 1/17/2019 | 1/17/2019 | 1/17/2019 | | PASS |
Michael Zawacki
|
|
|
Inlet protection needs to be pulled and then permit can be finalled.
|
General Inspection | 1/2/2019 | 1/2/2019 | 1/7/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/18/2018 | 12/18/2018 | 12/18/2018 | | PASS |
Michael Zawacki
|
|
|
All homes complete. Drain inlet protection still installed on some inlets, needs to be removed before permit will be closed.
|
General Inspection | 12/3/2018 | 12/3/2018 | 12/3/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/16/2018 | 11/16/2018 | 11/16/2018 | | PASS |
Michael Zawacki
|
|
|
Still DI protection on Taboo Pl. Tao, Hakkasan & Highland valley. One hom under construction on highland valley, landscaping has been completed.
|
General Inspection | 11/1/2018 | 11/1/2018 | 11/1/2018 | | PASS |
Andy J. Long
|
|
|
NO discharges or violations. Just need to remove DI bags on Taboo and then Highland Valley after last home is landscaped.
|
General Inspection | 10/17/2018 | 10/17/2018 | 10/17/2018 | | CANC |
Andy J. Long
|
|
|
|
Site Final | 10/2/2018 | 10/2/2018 | 10/9/2018 | P | NR |
Andy J. Long
|
|
|
DI bags still installed @ Taboo. WIP on homes on Highland Valley.
|
General Inspection | 10/2/2018 | 10/2/2018 | 10/2/2018 | | PEND |
Andy J. Long
|
|
|
will check for DI bag removal
|
General Inspection | 9/17/2018 | 9/17/2018 | 9/17/2018 | | CANC |
Andy J. Long
|
|
|
|
Site Final | 8/29/2018 | 8/31/2018 | 9/4/2018 | P | NR |
Andy J. Long
|
|
|
check for DI bags in East Valley
|
General Inspection | 8/28/2018 | 8/28/2018 | 8/29/2018 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 8/13/2018 | 8/13/2018 | 8/13/2018 | | PASS |
Michael Zawacki
|
|
|
All homes completed. Sent message to RP to remove DI protection so permit an be closed.
|
General Inspection | 7/27/2018 | 7/27/2018 | 7/27/2018 | | PASS |
Michael Zawacki
|
|
|
Last few homes on Taboo under construction. Site is clean. When Taboo done and neighborhood BMPs all removed ok to close permit.
|
General Inspection | 7/12/2018 | 7/12/2018 | 7/12/2018 | | PASS |
Michael Zawacki
|
|
|
Neighborhood about complete, only construction is on Taboo. No ESC issues. Can remove neighborhood BMPs from everywhere except Taboo.
|
General Inspection | 6/27/2018 | 6/27/2018 | 6/27/2018 | | PASS |
Michael Zawacki
|
|
|
Only remaining home construction is on Taboo. Inlet protection throughout rest ofsite can be removed.
|
General Inspection | 6/12/2018 | 6/12/2018 | 6/12/2018 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/28/2018 | 5/28/2018 | 5/29/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/11/2018 | 5/11/2018 | 5/11/2018 | | PASS |
Michael Zawacki
|
|
|
Inspected 5-10. Final phase under construction. Landscapers are storing materials on road. Overall site is clean and lots are being cleaned as finished.
|
General Inspection | 4/26/2018 | 4/26/2018 | 4/27/2018 | | PASS |
Andy J. Long
|
|
|
WIP on homes in East Valley on Taboo and Highland Valley. Subdivision BMPs installed. Job sites have permit signs and trash contained.
Request issued: - empty out DI bag on Highland Valley - remove DI bags on Hakkasan oncle last two units are landscaped/cleaned.
|
General Inspection | 4/11/2018 | 4/11/2018 | 4/12/2018 | | PART |
Michael Zawacki
|
|
|
Taboo street needs to be cleaned and inlets maintained. Landscapers are storing gravel on road.
|
General Inspection | 3/27/2018 | 3/27/2018 | 3/28/2018 | | PART |
Michael Zawacki
|
|
|
Lots of dirt on road by new construction on Hakkasan and Taboo. Rest of neighborhood is completed and clean.
|
General Inspection | 3/12/2018 | 3/12/2018 | 3/12/2018 | | PART |
Michael Zawacki
|
|
|
Majority of neighborhood is clean. Landscapers are on Hakkasans on rear of project. Load of landscapong rocks is on road, some trackout in area.
|
General Inspection | 2/23/2018 | 2/23/2018 | 2/23/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 2/8/2018 | 2/8/2018 | 2/8/2018 | | PEND |
Michael Zawacki
|
|
|
Dis need to be cleaned and some can be removed. Contacted Syman since they are listed as SWPPP contacts.
|
General Inspection | 1/24/2018 | 1/24/2018 | 1/25/2018 | | PART |
Michael Zawacki
|
|
|
DIs on corner of Ghost Bar & Boven are full and can be removed. DIs further up Ghost bar can also be removed, all homes in area completed. Rock & sod is being stored on Taboo. Homes on Hakkasan being built, some dirt and trash needs to be cleaned. Home work also on Tao. Pathway behind project BMPs holding up.
|
General Inspection | 1/9/2018 | 1/9/2018 | 1/10/2018 | | PART |
Michael Zawacki
|
|
|
Homes being framed on Hakkasan have piles of waste laying around. All foundations have been completed. Neighborhood BMPs in place. Majority of neighborhood clean and completed.
|
General Inspection | 12/25/2017 | 12/25/2017 | 12/26/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/8/2017 | 12/8/2017 | 12/8/2017 | | PASS |
Michael Zawacki
|
|
|
WIP on SFH. Each house has its own permit displayed. All fondations and drives poured. Some light tracking in neighborhood. Homesites have trash boxes and are clean. Path on rear of development has BMPs and is being stabalized.
|
General Inspection | 11/23/2017 | 11/23/2017 | 11/24/2017 | | PASS |
Michael Zawacki
|
|
|
WIP on SFH. Trackout has been swept and garbage is contained. Path behind neighborhood has wattle on slopes and has been hydro seeded.
|
General Inspection | 11/8/2017 | 11/8/2017 | 11/8/2017 | | PEND |
Michael Zawacki
|
|
|
WIP on SFH. Lots of tracking onto Hakkasan Ave.
|
General Inspection | 10/24/2017 | 10/24/2017 | 10/24/2017 | A | PASS |
Michael Zawacki
|
|
|
WIP on multiple homes all in different stages of completion. All foundations have been poured. Area is clean and free of dirt and waste. Foothill perimeter in good shape with wattles on the grades.
|
General Inspection | 10/11/2017 | 10/11/2017 | 10/13/2017 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 9/26/2017 | 9/26/2017 | 9/28/2017 | | PASS |
Andy J. Long
|
|
|
Subdivision BMPs installed. WIP on numerous SFH. Designated washout provided. Check trail area along foothills next inspection.
|
General Inspection | 9/11/2017 | 9/11/2017 | 9/19/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/25/2017 | 8/25/2017 | 8/25/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/7/2017 | 8/10/2017 | 8/18/2017 | P | PEND |
Andy J. Long
|
|
|
street sweeping?
|
General Inspection | 8/7/2017 | 8/7/2017 | 8/7/2017 | A | PART |
Andy J. Long
|
|
|
Trash at sites contained. Lots of excavation and foundation work occuring this week, so a thorough sweeping will be needed at end of week. Storm drains have sediment protection. Lined concrete washout on Taboo culdesac being utilized and has remaining capacity.
Partial for street sweeping request. Will follow up at end of week.
|
General Inspection | 8/1/2017 | 8/1/2017 | 8/2/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP on SFH. Trash is contained. Streets are clean, no trackout. Concrete washout ok and in use. Signs are posted. DIs okay. No corrections requested.
|
General Inspection | 6/30/2017 | 6/30/2017 | 6/30/2017 | P | PASS |
Melissa Jannusch
|
|
|
Trackout has been swept. Trash has been emptied. Corrections have been addressed.
|
Site Preparation | 6/28/2017 | 6/30/2017 | 6/30/2017 | P | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 6/28/2017 | 6/28/2017 | 6/28/2017 | | PART |
Melissa Jannusch
|
|
|
Hakkasan needs sweeping. Hakkasan and Skybar trash needs to be emptied and windblown trash picked up.
RP has sweeper scheduled for later this week. Plans to empty trash this week and will pick up windblown trash.
|
General Inspection | 6/13/2017 | 6/13/2017 | 6/13/2017 | P | PASS |
Melissa Jannusch
|
|
|
Sweeping occuring at time of inspection. WIP on SFH. No corrections requested.
|
General Inspection | 5/22/2017 | 5/30/2017 | 5/30/2017 | A | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/19/2017 | 5/22/2017 | 5/22/2017 | A | PART |
Melissa Jannusch
|
|
|
Tao Boven need to change DI bags. Sweeping needed. Other DI bags need to be changed soon.
|
General Inspection | 5/19/2017 | 5/19/2017 | 5/19/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/4/2017 | 5/4/2017 | 5/4/2017 | | CANC |
Andy J. Long
|
|
|
|
Tracking Control | 4/14/2017 | 4/19/2017 | 4/19/2017 | A | PASS |
Melissa Jannusch
|
|
|
Still some trackout but appears to have been swept. The sidewalks are cleaner. Continue to monitor trackout and encourage subs to sweep daily.
|
General Inspection | 4/3/2017 | 4/7/2017 | 4/7/2017 | A | PART |
Melissa Jannusch
|
|
|
Concrete washout maintenance has been performed. Subdivision still has trackout. Sweep trackout.
|
General Inspection | 4/3/2017 | 4/3/2017 | 4/3/2017 | | FAIL |
Melissa Jannusch
|
|
|
Sidewalks need sweeping. Concrete washout need maintenance.
|
General Inspection | 3/17/2017 | 3/17/2017 | 3/17/2017 | | FAIL |
Melissa Jannusch
|
|
|
WIP on SFH. Corrections requested. Sweep and preform concrete washout maintenance. Left message with RP requesting corrections.
|
General Inspection | 3/2/2017 | 3/2/2017 | 3/2/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP. Concrete washout in good condition. DI bags okay. No significant trackout. Dirt piles are back from sidewalk and contained on site. No corrections requested.
|
General Inspection | 2/15/2017 | 2/15/2017 | 2/16/2017 | | PASS |
Melissa Jannusch
|
|
|
No WIP. No corrections
|
General Inspection | 1/31/2017 | 1/31/2017 | 2/1/2017 | | PASS |
Melissa Jannusch
|
|
|
No corrections.
|
General Inspection | 1/16/2017 | 1/16/2017 | 1/24/2017 | | PASS |
Melissa Jannusch
|
|
|
SFHs. Inlets have sediment protection. No muddy discharges. Some construction activity. No corrections at this time. Check inlets for clogging next inspection.
|
General Inspection | 12/30/2016 | 12/30/2016 | 1/4/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/15/2016 | 12/15/2016 | 12/21/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/30/2016 | 11/30/2016 | 11/30/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/15/2016 | 11/15/2016 | 11/15/2016 | | PASS |
Andy J. Long
|
|
|
No new subdivsion devlopment activity. Lots in new phase have had drainage control earthen berms installed with intention to retain runoff on site. All inlets have sediment protection installed. Tahoe Homes utilizing lined concrete washout pit.
No corrections requested.
|
General Inspection | 10/28/2016 | 10/31/2016 | 11/1/2016 | P | PASS |
Andy J. Long
|
|
|
No erosion on subdivison slopes observed, no trackout from open areas. All new storm drains have inlet protection. Earthen berms constructed in new phase open lots to control/contain sheet flow runoff. Tahoe Homes has constructed new lined concrete washout. Approved.
|
General Inspection | 10/28/2016 | 10/28/2016 | 10/28/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled for 10/31. No issues observed yesterday in East Valley
|
General Inspection | 10/13/2016 | 10/13/2016 | 10/13/2016 | | PASS |
Andy J. Long
|
|
|
Phase II roads are now paved and have curb, gutter, sidewalk. New storm drains have sediment filter bags installed. No perimeter controls installed currenlty, grading of open parcel and catchment troughs seem to direct water inward to retain and allow infiltration.
Large stockpile in northeast corner of sub will need perimeter controls or to be moved.
No construction activity at time of inspection, no violations. SWPPP info posted.
|
General Inspection | 9/28/2016 | 9/28/2016 | 9/28/2016 | | PASS |
Andy J. Long
|
|
|
WIP on subdivsion. Currently crews installing walking path and playground up against foothills. No trackout outside of sub, no fugitive dust observed during construction or reported.
WIP on road work on HV Road, checking with ACHD on status of east side of road that has been damaged and patched. Response pending
|
General Inspection | 9/12/2016 | 9/13/2016 | 9/13/2016 | A | PASS |
Andy J. Long
|
|
|
No active grading occuring at time of inspection. Roads have been prepped for paving and connection to permanent storm drain system. No wind blown dust observed at 12:15 PM.
No trackout, roads have been swept after recent heavy activity. No corrections at this time.
|
General Inspection | 9/12/2016 | 9/12/2016 | 9/12/2016 | | CANC |
Andy J. Long
|
|
|
|
Tracking Control | 8/25/2016 | 8/26/2016 | 8/26/2016 | P | PASS |
Andy J. Long
|
|
|
Sweeper was ordered for yesterday and completed, another sweeper is scheduled for tonight.
|
Tracking Control | 8/25/2016 | 8/25/2016 | 8/25/2016 | P | PEND |
Andy J. Long
|
|
|
Request issued to have street sweeper at end of day. Active subdivision and dirt transfer from Ghost Bar to HV Road is occuring. Water truck being utilized for dust control is some of the problem. DIs in East Vally have sediment filters installed.
Will check for sweep up tomorrow...
|
Random Inspection | 8/22/2016 | 8/22/2016 | 8/22/2016 | P | PART |
Andy J. Long
|
|
|
Observed stock pile transfer occuring with inadequate dust suppression.
Water truck was on site, but had not been applied to stockpile to stop dust and wind blowing lots of dust on homes along HV Road.
Excavator stopped work and water truck came to spray stockpile and loading area. Dust control worked, excavator said they will keep it wet.
Initial violation corrected. Work may continue.
|
General Inspection | 8/11/2016 | 8/16/2016 | 8/16/2016 | A | PART |
Andy J. Long
|
|
|
Crews working on cutting road areas.
Correction needed:
No trackout but need to have water truck with its own designated driver. Verbal notice given to RP.
|
General Inspection | 8/11/2016 | 8/11/2016 | 8/11/2016 | | PASS |
Andy J. Long
|
|
|
WIP with site utlities. No violations. Will reinspect next week to review BMPs for road installation.
|
General Inspection | 7/27/2016 | 7/27/2016 | 7/28/2016 | | PEND |
Andy J. Long
|
|
|
Crews back on site working on new phase of East Valley. Limited work occuring, no dust but dirt is very loose. Will need to requied dust removal when watered down. Restrict traffic.
Will check next week for solution. No issues currently and no complaints yet...
|
General Inspection | 7/11/2016 | 7/11/2016 | 7/12/2016 | | PART |
Andy J. Long
|
|
|
WIP on sewer & water line installation on HV Road. Received dust complaint from neighbor. Dust not bad at time of inspection, worker using water to spray down stockpile of dirt being used for fill in the trench.
Corrections: - sweep roadways between work area and site staging area in EV subdivision. - continue to use water for dust control.
|
General Inspection | 6/24/2016 | 6/24/2016 | 6/24/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 6/9/2016 | 6/9/2016 | 6/10/2016 | | CANC |
Andy J. Long
|
|
|
no inspection conducted, site is currently inactive for subdivision devepment
|
Complaint Inspection | 5/25/2016 | 5/25/2016 | 5/25/2016 | P | PART |
Evan Jenkins
|
|
|
Dust Complaint
No Dust Observed. Recent Rain storms have all sediment compacted. Discussed with RP to keep water truck spraying water down during construction during warm days to reduce dust.
|
Random Inspection | 5/20/2016 | 5/20/2016 | 5/20/2016 | P | PASS |
Andy J. Long
|
|
|
Work has resumed for subdivision development. Crew onsite digging large subsurface drainage /infiltration pit at base of hill. No trackout or fugitive dust leaveing work area.
SFHs in progress on Ghost Bar. Two lined washouts provided to accomodate multiple foundations poured simultaneously. Trash bins provided, no discharges, DIs have sediment filter mats.
No corrections issued, approved.
|
General Inspection | 5/13/2016 | 5/13/2016 | 5/13/2016 | | PASS |
Andy J. Long
|
|
|
No new subdivision activity at East Valley phase 2-3. No fugitive wind blown dust observed, no recent complaints received. No trackout or discharges. SFHs in active phases are in compliance.
|
General Inspection | 4/28/2016 | 4/28/2016 | 4/28/2016 | | PASS |
Andy J. Long
|
|
|
No subdivsion construction activity. Active SFH construction in previously built East Vally phases. No fugitive dust issues observed or reported. No corrections at this time.
|
General Inspection | 4/13/2016 | 4/13/2016 | 4/13/2016 | | PASS |
Andy J. Long
|
|
|
No stormwater runoff issues along HV Road for East Valley Sub. Drainage improvement and erosion controls have worked well. No new subdivision activity occuring. No trackout, fugitve dust, or other issues observed. DIs within subdivision have filter mats installed.
No corrections.
|
General Inspection | 3/29/2016 | 3/29/2016 | 3/29/2016 | | PASS |
Andy J. Long
|
|
|
No subdivision work occuring at this time for next EV phase. No wind-blown dust or erosion issues observed. No corrections at this time.
|
Random Inspection | 3/14/2016 | 3/14/2016 | 3/14/2016 | P | PASS |
Andy J. Long
|
|
|
Stormwater improvements along HV Road handled rain storm well. No trackout, no subdivision work occuring, just Tahoe Homes working on SFH foundations. Permitted seperately. Lined washout being utilized.
No corrections issued.
|
General Inspection | 3/9/2016 | 3/9/2016 | 3/9/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/16/2016 | 2/22/2016 | 2/22/2016 | P | PASS |
Andy J. Long
|
|
|
No subdivision work occuring at this time. Site has perimeter sediment controls around open lots, DI bags; and road improvments along Highland Valley Road that have prevented illegal trespass and trackout.
No corrections issued at this time.
|
General Inspection | 2/15/2016 | 2/15/2016 | 2/16/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 1/29/2016 | 1/29/2016 | 1/29/2016 | | PASS |
Andy J. Long
|
|
|
No subdivision development activity. No trackout or loose sediment leaving site. On site stormwater system has sediment control BMPs installed. SFH work by Tahoe occuring in the first phase of East Valley.
|
General Inspection | 1/14/2016 | 1/14/2016 | 1/14/2016 | | PASS |
Andy J. Long
|
|
|
No muddy runoff from snowmelt. No corrections needed at this time.
|
General Inspection | 12/25/2015 | 12/25/2015 | 12/28/2015 | | CANC |
Andy J. Long
|
|
|
Christmas holiday
|
General Inspection | 12/10/2015 | 12/10/2015 | 12/10/2015 | P | PASS |
Andy J. Long
|
|
|
Post rainfall inspection. No BMP failures or turbid discharges offsite during second round of significant rain storms this week. No trackout. DIs have sediment protection. No corrections at this time.
|
Random Inspection | 12/7/2015 | 12/7/2015 | 12/7/2015 | P | PASS |
Andy J. Long
|
|
|
BMPs and stormwater management improvements along Highland Valley Road have prevent erosion and sediment runoff.
Approved.
|
General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 | | PASS |
Andy J. Long
|
|
|
Recent site improvements and corrective actions requested have kept runoff onsite with no turbid discharges observed. Access to cleared area off Highland Valley road above Taboo is not restricted and no further citizen complaints received.
No corrections requested at this time. Site is currently in compliance.
|
General Inspection | 11/10/2015 | 11/10/2015 | 11/10/2015 | P | PASS |
Andy J. Long
|
|
|
BMPs and roadside drainage improvements in East Valley contained sediment on site. No discharges or trackout observed. DIs have coir mat protection and perimeter berms have been installed to contain and direct sheet flow.
No recent complaints received, site currently in compliance.
|
Site Preparation | 10/26/2015 | 10/27/2015 | 10/27/2015 | P | DONE |
Andy J. Long
|
|
|
2:30 PM site meeting and walk through for winterization
Slopes will be tackified. Road shoulders are to have landscaping installed which will assist with sediment control. Upper area along HV Road to be bermed off in addition to a temporary drainage ditch. This area will also be hydro-mulched. This portion of project should be winterized within 2 weeks.
|
Conference | 10/23/2015 | 10/26/2015 | 10/26/2015 | A | CANC |
Andy J. Long
|
|
|
rescheduled for 10/27.
|
Conference | 10/23/2015 | 10/23/2015 | 10/23/2015 | P | DONE |
Andy J. Long
|
|
|
Work has resumed in East Valley Sub phase #2. Monday 10/26 meeting has been planned to discuss winterization and stabilization BMPs with RP including restricting access to area off HV road and providing stormwater channel.
|
Random Inspection | 10/19/2015 | 10/19/2015 | 10/19/2015 | P | FAIL |
Andy J. Long
|
|
|
Post precipitation inspection conducted at 4 PM Singificant sediment runoff from disturbed areas in EV phase 1 & 2, in particular at the northeast corner along HV Road as well rill erosion through banks and slopes in
No BMPS installed or implemented at site other than DI protection, resulting in sediment running off site with a storm rated at 0.10 - 0.25" in last 24 hours of inspection. With more rainfall and intensity situation would be much worse.
Corrections: 1. Meeting on site to discuss BMP installation 2. Clean roads, 3. No corrections or response has been made on the CN issued 10/14, other than notification work would resume. 4. Need to apply hydroseed and/or hydromulch slopes not actively being worked up. 5. No SWPPP signage or information found on site.
|
General Inspection | 10/14/2015 | 10/15/2015 | 10/15/2015 | P | FAIL |
Andy J. Long
|
|
|
No response from RP- developer in regards to Correction Requests (Tuesday - me, Evan - today) to schedule dust suppression application and/or hydroseed with tacifier. Area is dusty from traffic and windblown dust.
Additional controls:
1. No further equipment parking in the area of concern on HV Road.
2. Install fencing to control access to area (turn arounds, cement trucks, lost drives). Block access within subdivision on the unfinished portions. Note - issued request to Tahoe Homes to direct concrete truck and subcontractors not to use these roads.
3. Water truck to be onsite for all construction activity and further grading. No activity at site at time of inspection.
Written CN posted....
|
Conference | 10/12/2015 | 10/13/2015 | 10/14/2015 | P | PEND |
Andy J. Long
|
|
|
dust control stabilization on Highland Valley Road
|
Complaint Inspection | 10/12/2015 | 10/12/2015 | 10/12/2015 | P | PEND |
Andy J. Long
|
|
|
Dust complaint received via Code Enforcement call desk....
No significant dust at time of inspection, but met with HV Road resident to discuss issues. The wind is really picking up a lot of dust not only from the East Valley Sub but from the graded area on the west side of the road.
Appears work in this area is complete - checking the schedule. Plan is to issue CN to developer to stabilize with a tacifier or hydroseed mix.
|
General Inspection | 9/1/2015 | 9/1/2015 | 9/1/2015 | P | PEND |
Andy J. Long
|
|
|
WIP at East Valley phase 2 and road improvements of Highland Valley Roady. At time of inspection there was on a small activity installing stormwater infrastructure and utilities under the new road base for the eastern section of the subdivision. No trackout or discharges occuring. Correction: Cut hillside below Highland Valley has been inactive more than 2 weeks and no stabilization throiugh seeding or erosion control mats has occured. Site is currently out of compliance in that regard. Notified RP Jim Conger of the requirements and requesting a schedule for stabilization or BMP installation.
|
Complaint Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 | A | PART |
Andy J. Long
|
|
|
Inspection in response to "excessive dust tornado" complaint received by Code Enforcement.
At time of inspection Friday 10:00 AM there was no significant or continuous plumes of fugitive dust. There is a lot of wind at this site however, so the possibility of fugitve and current work on Highland Valley Road and Warm Springs is actively disturbing dirt and moving stockpiles.
There is a water truck onsite that was filling up when I arrived. Correction:
Much of the recently graded phase 2 that is not currently active does not have a dust suppresion application or tacifier. Need to schedule this for the out perimeter lots and recently cut hillside.
VM left to RP Jim Conger, will check back to see when it can be scheduled.
|
Random Inspection | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | PASS |
Andy J. Long
|
|
|
Inpsection conducted to check progress on Highland Vally road infrastructure improvements. No dust issues at time of inspection, water truck onsite but was not in use. No plumes observed.
Warm Srpings Road is currently closed for construction.
WIP. No corrections issued.
|
Complaint Inspection | 8/4/2015 | 8/4/2015 | 8/4/2015 | P | FAIL |
Evan Jenkins
|
|
|
Complaint: Developer cleared all vegetation on hillside, causing dust issue
Called RP Jim Conger to have him Tempporarily Stabilize recent graded lots along Highland Valley Rd and hillside. Left VM. Per BCC 8-17, disturbed areas setting for 14 days or longer, need either perminant or temporary stabilization: (Tackifier or Mulch/seeding) Talked with water truck driver onsite (Hi-Grade), he stated he will water it a few times per day to keep dust supressed. Issue isn't from construction, its from windstorms occuring after working hours.
|
Tracking Control | 7/10/2015 | 7/13/2015 | 7/13/2015 | A | PART |
Andy J. Long
|
|
|
Warm Springs at Highland Valley has been swept and temporary retaining holes/diversion have been built along Highland Valley lining the new EV phase.
Tao and Boven culdesac has been cleaned and DI bags changed.
Need to have sweeper come do another round as the dirt loosens.
|
Tracking Control | 7/10/2015 | 7/10/2015 | 7/10/2015 | P | PART |
Andy J. Long
|
|
|
Drainage channel along Highland Valley blew out onto Warm Springs. Also in East Valley #1 the southeast corner had sediment deposition on the streets.
RP called to alert ESC division about issue. Shovel crew is working on the street in EV #1. A sweeper tractor is coming to clean Warm Springs at noon per RP.
Does not appear muddy discharge extended into the drainage ditch on the south side of road.
Channel should have check dams or be lined with rip rap. Also does not appear there is a receiving gutter to convey water along the north side of Warm Springs to west...
Corrective actions/clean up is in progress. Will check back this afternoon. Warm Springs should be cleaned by early afternoon.
|
General Inspection | 7/9/2015 | 7/9/2015 | 7/9/2015 | P | PASS |
Andy J. Long
|
|
|
No sediment runoff blowouts to streets and gutters. Hillside remain stable with no rills or areas of concern observed. Appears that rain storm was not as strong at this end of the valley. BMPs in place were adequate. No corrections.
|
General Inspection | 6/23/2015 | 6/23/2015 | 6/23/2015 | P | PASS |
Andy J. Long
|
|
|
Grubbing and initial grading activity has been finished on the east side of the East Valley phase 2 project. No activity at time of inspection.
No trackout from site access points, no wind blown dust observed, no discharges or materials contained/stored at site.
Approved, no corrections at this time.
|
Site Preparation | 5/11/2015 | 5/12/2015 | 5/12/2015 | P | PASS |
Andy J. Long
|
|
|
Pre-con conducted Monday (5/11); check for silt fence perimeter control installation and initial phase of work
Fiber wattles installed around perimeter of new phase on the west side of phase 1. Phase 1 BMPs (inlet protection) is installed. Approved for site grading and grubbing.
|
Permit Ready to Issue | | | 5/12/2015 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 5/12/2015 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/12/2015 | | DONE |
|
|
|
|
Application received | | | 5/1/2015 | | |
|
|
|
|