General Inspection | 9/13/2016 | 9/13/2016 | 9/13/2016 | | PASS |
Andy J. Long
|
|
|
Home complete and occupied. Hillsides have been vegetated. No DI bag removal required due to new projects just activated across the street and downhill from the home. HIllside bond issued for permanent vegetation and stabilization. No further ESC inspections required, conditions satisfied.
|
DOC - Permit Finaled | 9/13/2016 | 9/13/2016 | 9/13/2016 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 8/26/2016 | 8/29/2016 | 8/29/2016 | P | CANC |
Andy J. Long
|
|
|
data entry error. no inspection.
|
General Inspection | 8/26/2016 | 8/26/2016 | 8/29/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/11/2016 | 8/11/2016 | 8/11/2016 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 7/27/2016 | 7/27/2016 | 7/28/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/12/2016 | 7/12/2016 | 7/12/2016 | | PEND |
Evan Jenkins
|
|
|
re-veg disturbed areas. No discharges leaving the site at this time.
|
General Inspection | 6/27/2016 | 6/27/2016 | 6/27/2016 | | PASS |
Evan Jenkins
|
|
|
WIP: No issues observed at this time
|
General Inspection | 6/10/2016 | 6/10/2016 | 6/10/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/26/2016 | 5/26/2016 | 5/26/2016 | | CANC |
Andy J. Long
|
|
|
|
Random Inspection | 5/11/2016 | 5/11/2016 | 5/11/2016 | P | PART |
Andy J. Long
|
|
|
Home structure is complete but yard and driveway are not yet installed. Workers building landscape retaining wall on front slope. No significant trackout, perimeter wattle is installed around site, and most of the front slope is not disturbed.
Corrections needed: - DI bags next to driveway exit are full and need to be changed. - Need to clean up minor blowout at the low corner of the lot and re-install wattle. - Connect roof drains if not all ready or install slope drain. May consider a hydromulch/tacifier on the area where erosion is occurning.
|
General Inspection | 5/4/2016 | 5/4/2016 | 5/4/2016 | | PASS |
Evan Jenkins
|
|
|
WIP: no esc issues observed at this time
|
General Inspection | 4/19/2016 | 4/19/2016 | 4/20/2016 | | PASS |
Evan Jenkins
|
|
|
re-veg needs to occur along with final stabilization. driveway also needs to be poured
|
General Inspection | 4/4/2016 | 4/4/2016 | 4/4/2016 | | PASS |
Andy J. Long
|
|
|
Perimter wattles keeping sediment on site, some minor erosion rills within parcel and on adajacent parcel to the right of the hose will need to be re-graded/raked out prior to putting down hydorseed.
No trackout, no discharges from site. Need to empty trash bin and also make sure that when the curb is cut for the driveway that the cooling water slurry is captured and treat as much as is practical.
|
General Inspection | 3/18/2016 | 3/18/2016 | 3/18/2016 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 3/3/2016 | 3/3/2016 | 3/3/2016 | | PASS |
Evan Jenkins
|
|
|
construction continues. No ESC violations/issues observed at time of inspection
|
General Inspection | 2/17/2016 | 2/17/2016 | 2/17/2016 | | PASS |
Daryl Spivey
|
|
|
|
General Inspection | 2/2/2016 | 2/2/2016 | 2/2/2016 | | PASS |
Andy J. Long
|
|
|
BMPs installed properly. WIP with regular housekeeping. Approved.
|
General Inspection | 1/15/2016 | 1/18/2016 | 1/19/2016 | A | PART |
Andy J. Long
|
|
|
Perimeter BMPs installed, no sediment runoff from site. Trash and materials are contained.
Trackout from grading equipment and loading/unloading should be swept up this week. Down hill storm drains have sediment protection installed.
|
General Inspection | 1/15/2016 | 1/15/2016 | 1/15/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 12/25/2015 | 12/25/2015 | 12/28/2015 | | CANC |
Andy J. Long
|
|
|
Christmas holiday
|
General Inspection | 12/9/2015 | 12/9/2015 | 12/9/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: No esc issues at this time
|
General Inspection | 11/20/2015 | 11/20/2015 | 11/20/2015 | | PASS |
Andy J. Long
|
|
|
Perimeter fiber wattles installed and staked down properly. Rock construction entrance and tracking pad is effectively controlling trackout. Downstream DI has sediment filter bags.
No corrections at this time.
|
General Inspection | 10/13/2015 | 10/13/2015 | 10/13/2015 | P | PASS |
Andy J. Long
|
|
|
WIP. Perimeter fiber wattles are still installed and trenched in. No sediment leaving site to sidewalks or gutters.
Tracking pad BMP has been installed at entrance, permit is posted, and trash and materials are contained on site. No issues, no corrections requested. Approved.
|
General Inspection | 6/25/2015 | 6/25/2015 | 6/25/2015 | A | PASS |
Andy J. Long
|
|
|
ESC permit sign posted. Perimeter gator guard wattle installed and working effectively. Some minor trackout on sidewalk can be swept this week during housekeeping..
No sediment leaving site. Approved.
|
Issue & PRINT permit SFD | | | 6/9/2015 | | DONE |
|
|
|
|
Random Inspection | 5/27/2015 | 5/27/2015 | 5/27/2015 | A | PASS |
Andy J. Long
|
|
|
Perimeter wattle and grading BMP of vegetation preservation kept all sediment on this foothills home site during the heavy Thunderstorm.
Permit sign posted, no trackout, BMPs installed. Approved.
|
Site Preparation | 5/19/2015 | 5/20/2015 | 5/19/2015 | A | PASS |
Andy J. Long
|
|
|
John Phone #: ###-####
BMPs installed per ESC plan. Gatorgaurd wattles properly staked and backfilled installed as perimeter sediment control.
Hillside slopes have been previously hydroseeded so preservation of existing vegetation as much as possible will be a BMP.
A new driveway apron will need to be cut so I cautioned RP/GC to contain slurry. DI bags are installed.
Approved. Will start grading and earthwork for retaining walls.
|
Override - Parcel Holds | 5/19/2015 | 1/1/1900 | 5/19/2015 | | |
|
|
|
esc prep
|
Override - Parcel Holds | | | 5/19/2015 | | |
|
|
|
|
Issue & PRINT permit SFD | | | 5/19/2015 | | DONE |
|
|
|
|
Application received | | | 5/18/2015 | | |
|
|
|
|
Routing - Erosion and Sediment | 5/18/2015 | | 5/18/2015 | | DONE |
Andy J. Long
|
|
|
ESC plan and site map submitted and approved. Valid PD and RP designated. ESC plan covers construction of retaining walls and the new home.
|