Site Final | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PASS |
Andy J. Long
|
|
|
Work complete. Drive through lane paved and completed. Jimmy Johns open for business. ESC permit conditions satisfied.
|
General Inspection | 3/10/2016 | 3/10/2016 | 3/10/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/6/2016 | 1/6/2016 | 1/6/2016 | | PASS |
Andy J. Long
|
|
|
WIP. Cut concrete area below grade of rest of paved parking lot area for strip mall and is blocked off. No trackout or muddy runoff from site area. No corrections.
|
Site Preparation | 11/4/2015 | 11/5/2015 | 11/5/2015 | A | PASS |
Andy J. Long
|
|
|
Garrett Phone #: ###-####
Tenant improvement to add drive thru to sandwich shop at south end of the Shopko-Gateway center. Two parking lot storm drains have been fitted with sediment filter bags. WIP. Low risk surrounded on all side by pavement and minimal excavation.
|
Permit Ready to Issue | | | 11/3/2015 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 11/3/2015 | | DONE |
|
|
|
|
Application received | | | 6/22/2015 | | |
|
|
|
|