Site Final | 5/18/2016 | 5/18/2016 | 5/18/2016 | P | PASS |
Andy J. Long
|
|
|
Construction complete, home landscaped and stabilized.. DI bag on Liberty and Post removed as requested. Gutter was swept.
|
Aging Inspection | 5/12/2016 | 5/12/2016 | 5/12/2016 | | PEND |
Andy J. Long
|
|
|
Alley and curb work occuring around site. DI bag still installed. Need to complete work, sweep up and remove DI bag.
|
Site Final | 3/7/2016 | 3/8/2016 | 3/8/2016 | P | FAIL |
Jim Sly
|
|
|
Complete landscaping
|
Issue & PRINT permit SFD | | | 9/14/2015 | | DONE |
|
|
|
|
Application received | | | 8/4/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 4 2015 11:04AM
|