DOC - Permit Finaled | 10/17/2016 | 10/17/2016 | 10/17/2016 | P | PASS |
Andy J. Long
|
|
|
Home complete, landscaped, and occupied. No ESC requests, all permits finaled.
|
Aging Inspection | 9/20/2016 | 9/20/2016 | 9/20/2016 | | PASS |
Andy J. Long
|
|
|
WIP. No violations. Subdivision BMPs for DHE are installed. Permit sign posted.
|
Aging Inspection | 7/20/2016 | 7/20/2016 | 7/20/2016 | | PASS |
Andy J. Long
|
|
|
WIP. Near completion. Needs landscaping and trash haul off. No spills, discharges or other issues.
|
Aging Inspection | 5/19/2016 | 5/19/2016 | 5/19/2016 | | PASS |
Andy J. Long
|
|
|
WIP. Needs landscaping/stabilization. Subdivsion BMPs installed. Approved.
|
Aging Inspection | 3/17/2016 | 3/17/2016 | 3/17/2016 | | PASS |
Andy J. Long
|
|
|
WIP. Subdivsion BMPs installed. No trackout or discharges. No corrections.
|
Site Preparation | 11/12/2015 | 11/12/2015 | 11/12/2015 | P | PASS |
Andy J. Long
|
|
|
Clint Phone #: ###-####
Permit sign is posted at site. Subdivision BMPs installed and workers gaining access to site via alley and staying off landscaping.
BMPs include lined concrete washout with sign, DI sediment bag protection, and straw wattles have been installed at the base of both Tahoe blocks on both sides of Brookridge.
No violations observed. Approved for excavation.
|
Issue & PRINT permit SFD | | | 9/1/2015 | | DONE |
|
|
|
|
Application received | | | 8/11/2015 | | |
|
|
|
|