Site Final | 11/5/2015 | 11/5/2015 | 11/5/2015 | P | PASS |
Andy J. Long
|
|
|
Offsite utility work for River Heights #7 is complete. Temp BMPs will remain for the commencement of the full project, which will be covered under ESC15-01288. No active construction. Site is stable, permit conditions satisfied.
|
General Inspection | 10/8/2015 | 10/8/2015 | 10/8/2015 | P | PASS |
Andy J. Long
|
|
|
Work complete, road has been patched. Staging area will remain until subdivision grading will start on River Heights phase #7. No loose dirt on road. Temporary sediment control wattles are installed around area of work. No corrections, no issues at site observed.
|
Site Preparation | 9/18/2015 | 9/18/2015 | 9/18/2015 | P | PASS |
Andy J. Long
|
|
|
Staging area is prepped and the work area on the roadway has a downslope sediment barrier in the form of a trenched and staked wattle. Permit sign and ESC plan binder are located on site. Rock has been installed for an entrance to the staging area to reduce trackout.
Roadway and shoulders will need to be swept upon completion to remove loose sediment from the work.
Wattle should be removed and area where trenched compacted at the end of the project, unless otherwise discussed at that time. Approved for construction.
|
Application received | | | 9/18/2015 | | |
|
|
|
|
Routing - Erosion and Sediment | 9/18/2015 | | 9/18/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance).
Offsite Erosion & Sediment ONLY: (OFFSITE WORK ONLY), Until Grading Permit/ESC Permit is Issued. This portion is 1.25 Acres in Size
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/18/2015 | | |
|
|
|
|
Permit Ready to Issue | | | 9/18/2015 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 9/18/2015 | | DONE |
|
|
|
|