Site Final | 5/24/2016 | 5/25/2016 | 5/25/2016 | A | PASS |
Andy J. Long
|
|
|
New path complete and open to public. Old path area has revegetated and site is stable. No DI bags remaining on MS4 inlet on Pioneer. ESC permit satisfied.
|
Aging Inspection | 5/20/2016 | 5/20/2016 | 5/24/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 | A | PASS |
Andy J. Long
|
|
|
WIP on bricklaying for path. No uncontained stockpiles or materials. No muddy runoff. Section between Greenbelt and parking lot is complete. Parking lot storm drain receiving runoff from surrounding paved areas has inlet protection. No corrections issued at this time.
|
General Inspection | 11/17/2015 | 11/17/2015 | 11/17/2015 | P | PASS |
Andy J. Long
|
|
|
Pioneer Path corridor is in progress. No trackout or sediment leaving construcion area. Area DIs have sediment protection due to work on the Payette Brewery project adjacent to pathway. No violations or issues observed.
|
Site Preparation | 10/15/2015 | 10/16/2015 | 10/16/2015 | A | PASS |
Evan Jenkins
|
|
|
William Phone #: ###-####
Approved for Construction
|
Issue & PRINT permit COM | | | 10/15/2015 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/15/2015 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 9/30/2015 | | 10/1/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
Project constists of demolition, grading and construction of a mulit-use pathway in the City. Grading will predominately be cut for the proposed pathway with removal of existing asphalt, existing base courses, surficial soils and haul off.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2015 | | |
|
|
|
|
Permit Ready to Issue | | | 10/1/2015 | | DONE |
|
|
|
all requirements met
|
Telephone call | | | 10/1/2015 | | DONE |
|
|
|
called Randy (Scott's Brother)- told him permit is ready and fees due
|
Application received | | | 9/30/2015 | | |
|
|
|
|