Site Final | 4/29/2016 | 5/2/2016 | 5/4/2016 | P | PASS |
Andy J. Long
|
|
|
Construction complete, BLD finaled. Homeowner in process of installing irrigation line for garden area, so some dirt within vegetated yard. No sediment or other materials leaving site. No further inspections required.
|
Aging Inspection | 4/29/2016 | 4/29/2016 | 4/29/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final next week. Project is complete.
|
Site Preparation | 10/7/2015 | 10/8/2015 | 10/8/2015 | A | PASS |
Andy J. Long
|
|
|
Vaughn-would like to meet as early as possible Phone #: ###-####
Site walk through with RP-GC and architect. ESC sign to be posted at front of driveway. Existing driveway to be construction entrance. Addition in the back yard, patio in the front yard. No MS4 in area. Main BMP will be housekeeping, sweeping, and concrete washout containment on site.
|
Application received | | | 10/7/2015 | | |
|
|
|
|
Permit Ready to Issue | | | 10/7/2015 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 10/7/2015 | | DONE |
|
|
|
|