Site Final | 7/20/2017 | 7/20/2017 | 7/20/2017 | P | PASS |
Melissa Jannusch
|
|
|
|
General Inspection | 7/20/2017 | 7/20/2017 | 7/20/2017 | | PASS |
Melissa Jannusch
|
|
|
Project complete. Okay to final
|
General Inspection | 7/5/2017 | 7/5/2017 | 7/5/2017 | | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 6/20/2017 | 6/20/2017 | 6/20/2017 | | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 6/5/2017 | 6/5/2017 | 6/5/2017 | | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 5/19/2017 | 5/19/2017 | 5/19/2017 | | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 5/4/2017 | 5/4/2017 | 5/4/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/19/2017 | 4/19/2017 | 4/19/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/4/2017 | 4/4/2017 | 4/4/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/20/2017 | 3/20/2017 | 3/20/2017 | | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 3/3/2017 | 3/3/2017 | 3/3/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 2/16/2017 | 2/16/2017 | 2/21/2017 | | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 2/1/2017 | 2/1/2017 | 2/6/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/17/2017 | 1/17/2017 | 1/19/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/2/2017 | 1/2/2017 | 1/3/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/16/2016 | 12/16/2016 | 12/21/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/1/2016 | 12/1/2016 | 12/1/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/16/2016 | 11/16/2016 | 11/16/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/1/2016 | 11/1/2016 | 11/1/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/17/2016 | 10/17/2016 | 10/17/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/30/2016 | 9/30/2016 | 9/30/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/15/2016 | 9/15/2016 | 9/15/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/31/2016 | 8/31/2016 | 8/31/2016 | | PASS |
Andy J. Long
|
|
|
WIP on private estate poolhouse. No violations observed.
|
General Inspection | 8/16/2016 | 8/16/2016 | 8/16/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/13/2016 | 7/13/2016 | 7/13/2016 | | PASS |
Evan Jenkins
|
|
|
|
General Inspection | 6/28/2016 | 6/28/2016 | 6/28/2016 | | PASS |
Andy J. Long
|
|
|
|
Site Preparation | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | PASS |
Andy J. Long
|
|
|
Bob Phone #: ###-####
Project supervisor Rod onsite for walk through. Perimeter wattles installed around future pool & pool house site. Flat area, low runoff risk. No work adjacent to river or channels.
Reviewed ESC permit conditions. Approved for construction.
|
Issue & PRINT permit SFD | | | 3/11/2016 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 1/6/2016 | | 1/6/2016 | | PASS |
Andy J. Long
|
|
|
ESC site map and narrative submitted and approved. Valid Plan Designer and Responsible Person designated.
|
Application received | | | 10/19/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 19 2015 1:57PM
|