Site Final | 11/12/2015 | 11/12/2015 | 11/12/2015 | P | PASS |
Andy J. Long
|
|
|
Cody ###-####
Area of excavation has been paved over/stabilized. No loose sediment or temporary BMPs left on site. Permit finaled.
|
Site Preparation | 10/30/2015 | 10/30/2015 | 10/30/2015 | P | PASS |
Andy J. Long
|
|
|
Stinker soil removal...
Work to begin Monday. 2 day project to remove contaminated soils. Excavated trench will be loaded into containment barrels and hauled away. Remaining soils will be vacuumed up with Vac truck and disposed of legally at landfill.
Permit sign posted at area of work. Approved.
|
Permit Ready to Issue | | | 10/30/2015 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 10/30/2015 | | DONE |
|
|
|
|
Application received | | | 10/28/2015 | | |
|
|
|
|
Routing - Erosion and Sediment | 10/28/2015 | | 10/28/2015 | | PASS |
Evan Jenkins
|
|
|
Excavate an area approximatel 2ft by 30ft to a depth of approx six feet. Contaminated soils will be immediately placed into 55 gallon barrels and taken to land use farm south of town. Then clean soils will be backfilled to the ground surface and compacted.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2015 | | |
|
|
|
|
Permit Ready to Issue | | | 10/28/2015 | | DONE |
|
|
|
|
Telephone call | | | 10/28/2015 | | DONE |
|
|
|
Spoke with Cody informing him that the permit is ready and the fee amount that is due
|