Aging Inspection | 7/14/2016 | 7/14/2016 | 7/14/2016 | | PASS |
Evan Jenkins
|
|
|
|
DOC - Permit Finaled | 7/14/2016 | 7/14/2016 | 7/14/2016 | P | PASS |
Evan Jenkins
|
|
|
Project Complete ESC Conditions Satisfied
|
Random Inspection | 5/13/2016 | 5/13/2016 | 5/13/2016 | A | PASS |
Bob Reichert
|
|
|
looked ok
|
Site Preparation | 1/5/2016 | 1/5/2016 | 1/5/2016 | P | PART |
Andy J. Long
|
|
|
Inspection requested via web by Erby Gonzales
New lined and designated concrete washout provided for new set of foundations in Mill District Square. Storm drain inlets on streets have sediment filter bags installed and with good capacity. Trash at active sites is contained.
Approved to start but correction needed this week:
- install DI bag in storm drain in the alley at the soutn end of Woodcraft. Will sheet flow from an area with loose dirt and by the framing carpenters so lots of sawdust.
|
Permit Ready to Issue | | | 12/10/2015 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 12/10/2015 | | DONE |
|
|
|
|
Application received | | | 11/4/2015 | | |
|
|
|
|