Site Final | 10/7/2016 | 10/12/2016 | 10/12/2016 | A | PASS |
Andy J. Long
|
|
|
10:30 AM with Shane and Jesse
Scope of project complete. Temp BMPs (DI bag on Clubview) and wattles removed. ESC permit conditions satisfied. No further inspections required.
Note: some ongoing work by landscaping crews and interior park path installment remains. Boise Parks n Rec will continue to supervise. Temp construction fence and project sign will be removed before park opening in November.
|
General Inspection | 9/23/2016 | 9/23/2016 | 9/23/2016 | | PASS |
Andy J. Long
|
|
|
Park lanscaping in progress. RP Jesse on site supervising. BMPs installed; no trackout from parking lot staging area to Clubview
|
General Inspection | 9/8/2016 | 9/8/2016 | 9/8/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/24/2016 | 8/24/2016 | 8/24/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/29/2016 | 7/29/2016 | 7/29/2016 | P | PASS |
Andy J. Long
|
|
|
Boise Hills Park project is currently inacvited. BMPs installed, ESC permit posted. No issues at site.
|
Random Inspection | 7/12/2016 | 7/12/2016 | 7/12/2016 | A | PASS |
Daryl Spivey
|
|
|
|
General Inspection | 6/24/2016 | 6/24/2016 | 6/24/2016 | P | PASS |
Andy J. Long
|
|
|
WIP. BMPs installed, vegetative perimeters have been preserved. No fugitive dust, trackout or other issues. No complaints received by division. Approved.
|
General Inspection | 3/29/2016 | 3/29/2016 | 3/29/2016 | P | PASS |
Andy J. Long
|
|
|
Re-grading and distribution of the stockpile at Boise Hills Park is now complete. No activity at time of inspection but project is not yet complete.
No trackout or discharges, permit sign posted, and BMPs installed. No corrections needed.
|
Site Preparation | 3/10/2016 | 3/10/2016 | 3/10/2016 | P | CANC |
Andy J. Long
|
|
|
data entry error
|
Site Preparation | 3/2/2016 | 3/2/2016 | 3/2/2016 | P | PASS |
Andy J. Long
|
|
|
RP on site. Reieweed ESC plan. BMPs installed include an angular rock construction entrance and a DI bag on the storm drain on Clubview.
Vegetative perimeter with grass and trees are to be undisturbed, creating a sediment barrier. Grading will be done to direct sheet flow inward for onsite retention. Current stockpile is to be spread across the park area, no off haulig required.
Approved for construction. Permit sign posted on billboard at site entrance.
|
Issue & PRINT permit COM | | | 3/2/2016 | | DONE |
|
|
|
|
Application received | | | 2/9/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 9 2016 4:40PM
|