Site Final | 6/7/2016 | 6/7/2016 | 6/7/2016 | P | PASS |
Andy J. Long
|
|
|
Final walk through conducted. All MS4 inlets on Capitol/Vista curve have been removed. Sidewalk and gutter swept. Staging area removed and no materials remaining on site. ESC permit conditions satisfied. Stairway with construction barricade will have railing installed next week.
|
General Inspection | 5/18/2016 | 5/18/2016 | 5/18/2016 | P | PASS |
Andy J. Long
|
|
|
Platt Gardens project is near completion. Sidewalk path has been poured, curb was cleaned and DI bag is still installed. No violations observed.
|
General Inspection | 4/25/2016 | 4/25/2016 | 4/25/2016 | P | PASS |
Andy J. Long
|
|
|
WIP. Perimeter wattles and regular sweeping BMPs are being utilized at site. Some concrete cutting is occuring using water to control dust. No uncontained slurry discharges observed.
Permit sign posted, staging area is clean. No corrections at this time.
|
Site Preparation | 3/29/2016 | 3/29/2016 | 3/29/2016 | P | PASS |
Andy J. Long
|
|
|
Platt Gardens @ 9 AM
Site walk-through inspection conduct with RP and PD
Perimter wattles and construction fencing installed per ESC plan. New sidewalk will be installed around the norther loop of the park next to Capitol Blvd. DI filers bags properly instsalled.
Equipment staging and washout facility to located in the dirt parking lot to the west of the Depot.
Wattles are not yet staked because today the existing grass is going to be stripped.
Approved for construction.
|
Issue & PRINT permit COM | | | 3/25/2016 | | DONE |
|
|
|
|
Application received | | | 2/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 15 2016 9:18AM
|