DOC - Permit Finaled | 8/9/2016 | 8/9/2016 | 8/9/2016 | P | PASS |
Andy J. Long
|
|
|
Demo phase complete. New fire station in progress with ESC permit # ESC16-00448. Site is in compliance.
|
General Inspection | 6/21/2016 | 6/21/2016 | 6/21/2016 | P | PASS |
Andy J. Long
|
|
|
Station has been demolished and materials hauled away. No activity. Permit sign posted at Overland and Atlantic. Site surrounding with construction fencing and DIs have sediment filter mats installed.
ESI will build new station and be covered under ESC16-00448.
|
Site Preparation | 6/9/2016 | 6/9/2016 | 6/9/2016 | P | PASS |
Andy J. Long
|
|
|
Jill Phone #: ###-####
BMPs installed including sediment control mats on DIs, perimeter wattle along the south border, and construction fencing with dust screens.
Permit posted. Approved for demolition. Water supply to be onsite to control dust.
|
Permit Ready to Issue | | | 6/8/2016 | | DONE |
|
|
|
|
Issue & PRINT permit COM | | | 6/8/2016 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/25/2016 | | 3/28/2016 | | DONE |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
Demolition of commercial structure for future new Firestation # 8
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2016 | | |
|
|
|
|
Application received | | | 3/25/2016 | | |
|
|
|
|