Site Final | 3/10/2017 | 3/10/2017 | 3/10/2017 | A | PASS |
Andy J. Long
|
|
|
Disturbed area along access driveway is now vegetated. Site is stabilized, no temporary BMPs remaining. ESC conditions satisfied.
|
General Inspection | 1/30/2017 | 1/30/2017 | 2/1/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/13/2016 | 12/13/2016 | 12/13/2016 | | PASS |
Andy J. Long
|
|
|
Base of tower and enclosure complete. Access path paved and disturbed area seeded. Top of tower not yet installed.
|
General Inspection | 10/25/2016 | 10/25/2016 | 10/25/2016 | | PASS |
Andy J. Long
|
|
|
Cell tower project near completion. Tower not fully erected but access drive has been completed and lease are seeded. No trackout or discharges. No activity at time of inspection.
|
General Inspection | 8/15/2016 | 8/15/2016 | 8/15/2016 | P | PASS |
Andy J. Long
|
|
|
WIP on cell tower. No trackout. Permit sign posted, stabilzed entrance provided.
|
Issue & PRINT permit COM | | | 6/13/2016 | | DONE |
|
|
|
|
Application received | | | 4/12/2016 | | |
|
|
|
|