Site Final | 8/4/2017 | 8/9/2017 | 8/14/2017 | A | PASS |
Andy J. Long
|
|
|
Construction complete, no temp BMPs remaining. ESC permit conditions satisfied.
|
General Inspection | 8/4/2017 | 8/4/2017 | 8/4/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/19/2017 | 6/19/2017 | 6/21/2017 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/2/2017 | 5/2/2017 | 5/2/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/17/2017 | 3/17/2017 | 3/17/2017 | | PASS |
Melissa Jannusch
|
|
|
Work resuming after a break due to winter conditions. Site map available. RP will reinstall DI bag. Concrete washout installed. Sign posted. Okay to start.
|
General Inspection | 1/30/2017 | 1/30/2017 | 1/30/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/13/2016 | 12/13/2016 | 12/14/2016 | | CANC |
Andy J. Long
|
|
|
|
Change Status (ISS) | | | 11/29/2016 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 11/23/2016 | | 11/23/2016 | | DONE |
Andy J. Long
|
|
|
New ESC plan submitted and new RP designated. Valid Plan Designer.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/23/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/23/2016 | | DONE |
|
|
|
called Bryan to let know permit fis ready and how much is owed-left message
|
General Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 | | PASS |
Andy J. Long
|
|
|
WIP on rear equipment yard grading. No trackout. Grade below EoP and stormwater retained onsite
|
Issue & PRINT permit COM | | | 5/3/2016 | | DONE |
|
|
|
|
Application received | | | 4/15/2016 | | |
|
|
|
|