Site Final | 8/22/2017 | 8/23/2017 | 8/25/2017 | A | PASS |
Andy J. Long
|
|
|
Home complete, landscaped, and no temporary BMPs or loose materials remaining. All permits finaled.
|
General Inspection | 6/29/2017 | 6/29/2017 | 6/29/2017 | P | PASS |
Andy J. Long
|
|
|
WIP on perimeter stone wall. Cutting saw is hooked up to home water connection. No fugitive stone dust observed at time of inspection.
No discharges or trackout from site. Yard inside wall is not yet landscaped.
|
General Inspection | 5/16/2017 | 5/16/2017 | 5/16/2017 | A | PASS |
Andy J. Long
|
|
|
Landscaping in progress, project near completion. Gutter and sidewalk are free of loose dirt and other materials. No loose trash or building materials.
|
Random Inspection | 3/31/2017 | 3/31/2017 | 3/31/2017 | P | PASS |
Andy J. Long
|
|
|
WIP. Permit sign posted. HOme near completion but not yet landscaped/stabilized. No sediment runoff or trackout from site.
|
Aging Inspection | 2/1/2017 | 2/1/2017 | 2/1/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP. Sign posted. no trackout. Snow covered conditions. No corrections
|
General Inspection | 12/1/2016 | 12/1/2016 | 12/1/2016 | A | PASS |
Andy J. Long
|
|
|
WIP on exterior finishes and insterior. Sidewalk and gutters are free of trackout, accumulated sediment, and no discharges. Trash contained. Approved.
|
General Inspection | 9/13/2016 | 9/13/2016 | 9/13/2016 | A | PASS |
Andy J. Long
|
|
|
WIP on SFH. No loose sediment or other materials in sidewalks and gutters surrounding project. Permit sign posted on Kipling, trash contained. No corrections needed.
|
General Inspection | 8/23/2016 | 8/23/2016 | 8/23/2016 | P | PASS |
Andy J. Long
|
|
|
Framing work in progress. No trackout to sidewalk or street. Trash contained. No loose dirt or other materials in gutters around project. Approved.
|
General Inspection | 6/28/2016 | 6/28/2016 | 6/28/2016 | P | PASS |
Andy J. Long
|
|
|
Foundation for SFH has been poured. No activity at time of inspection, but site is very clean. No trackout or loose sediment on surrounding sidewalks and gutters. Permit sign is posted on Kipling. No corrections issued.
|
Site Preparation | 5/25/2016 | 5/25/2016 | 5/25/2016 | A | PASS |
Andy J. Long
|
|
|
note: send RP class schedule
Permit sign posted. Closed out demo permit.
Backfill currently being hauled offsite to prevent sediment runoff. Wide flat sidewalk along Crescent Rim should prevent runoff but may require wattles if an issue.
Requested that sidewalk be swept today. DI is over 200 M west on Crescent Rim, no bag requested.
|
Issue & PRINT permit SFD | | | 5/24/2016 | | DONE |
|
|
|
|
Application received | | | 5/4/2016 | | |
|
|
|
|