Site Final | 7/18/2017 | 7/18/2017 | 7/18/2017 | A | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 7/18/2017 | 7/18/2017 | 7/18/2017 | P | PASS |
Jim Sly
|
|
|
|
Site Preparation | 7/18/2017 | 7/18/2017 | 7/18/2017 | A | CANC |
Jim Sly
|
|
|
|
General Inspection | 6/6/2017 | 6/6/2017 | 6/6/2017 | | CANC |
Andy J. Long
|
|
|
|
BMP Violation | 4/14/2017 | 4/18/2017 | 4/19/2017 | A | PASS |
Melissa Jannusch
|
|
|
Paint has been cleaned up. No other ESC issues.
|
BMP Violation | 4/7/2017 | 4/11/2017 | 4/14/2017 | P | CANC |
Andy J. Long
|
|
|
|
Random Inspection | 4/7/2017 | 4/7/2017 | 4/7/2017 | P | FAIL |
Andy J. Long
|
|
|
Uncontained paint and other material washout on corner of Ardyce and Fastwater
Correction request to clean up and train painters to use a designated washout area.
|
General Inspection | 3/14/2017 | 3/14/2017 | 3/14/2017 | P | PASS |
Melissa Jannusch
|
|
|
DI protection OK. Trash containment good. No trackout onto road. No corrections requested.
|
General Inspection | 2/9/2017 | 2/9/2017 | 2/9/2017 | | PASS |
Melissa Jannusch
|
|
|
The inlet bags have been cleaned. Parking lot is now paved and being used as construction entrance. Sign is posted. Abram is clean of construction trackout only dirty from safety sand. No corrections.
|
General Inspection | 12/21/2016 | 12/21/2016 | 12/27/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 | A | PART |
Andy J. Long
|
|
|
WIP on Dropzone Apartments. Construction entrance installed, lined washout provided, permit signs posted.
RP Colby w/ CBH is onsite. No trackout or discharges observed.
Verbal Correction Request: - sweep Abram Street - install new inlet bag on Abram at Sweetwater - replace inlet bags on Fastwaster - lengthen construction entrance to 50 ft
RP stated will install new inlet bags today (x3) and order street sweeper for Thursday or Friday.
|
General Inspection | 10/26/2016 | 10/26/2016 | 10/26/2016 | A | PART |
Andy J. Long
|
|
|
WIP on Dropzone Apartments. Construction entrance installed, lined washout provided, permit signs posted.
RP Colby w/ CBH is onsite. No trackout or discharges observed.
Verbal Correction Request: - sweep Abram Street - install new inlet bag on Abram at Sweetwater - replace inlet bags on Fastwaster - lengthen construction entrance to 50 ft
RP stated will install new inlet bags today (x3) and order street sweeper for Thursday or Friday.
|
General Inspection | 10/20/2016 | 10/24/2016 | 10/26/2016 | P | CANC |
Andy J. Long
|
|
|
rescheduled 10/26
|
General Inspection | 10/20/2016 | 10/24/2016 | 10/26/2016 | P | CANC |
Andy J. Long
|
|
|
Construction entrance follow up at Dropzone apartments
rescheduled 10/26
|
Site Preparation | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PASS |
Andy J. Long
|
|
|
Colby Phone #: ###-####
Dropzone apartment grading and initial excavation conductied under main site permit ESC16-00696
Four 8-plex apartment buildings to be erected. Site access and parking not yet paved. Asphalt scheduled for 2nd week of November.
Reviewed ESC conditions with RP Colby, requested 4 or more trash containment bins and designated scrap wood and material staging zone with stabilized entrance. Surrounding storm drains have sediment filter bags installed for Dropzone Sub SFHs by CBH
Foundation construciton and vertical construction to start on Monday. Follow up inspection for construction entrance and washout facility on Monday 10/24 PM
|
Permit Ready to Issue | | | 10/13/2016 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 10/13/2016 | | DONE |
|
|
|
|
Application received | | | 5/20/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 20 2016 9:42AM
|